Bogus EF dates...

David AndreottiMember for 21 years 3 months
Created
3
2
0
I have a started activity, with a remaining duration. I’ve broken the predecessor and successor ties, rescheduled, and am still getting an early finish that does not come from the remaining duration. I’ve run PFXW, recalced many times, etc. Help??

angant

3 replies

Oldest first
  1. 0
    Ronald Winter ·
    Do you have an Expected Finish constraint posted for that activity?
  2. 0
    David Andreotti ·
    No, I checked all that.

    It turned out to be a topic activity that had a predecessor! I ran the no-topic utility, and organized the schedule in suretrak in outline mode, then outdented everything. Now my RD is driving my EF.
  3. 0
    Sukumaran Subaramaniyan ·
    Go to Project Overview > check Project Must Finish By. If you imposed any finish date constraint, remove it and re-calculate the schedule.

    Regards.