What is a "run date" and how is it differentiated from the Data Date.

1 reply

Oldest first
  1. 0
    Bijaya Bajracharya ·
    Run date = the date on which the project was last run (opened). Any change made in activity (for example progressing, changing original or remaining durations)will have effect only in that activity until F9 is pressed (rescheduled).