P3.1 Planned Percentage

Gavin MorrisMember for 21 years 9 months
Created
3
1
0
Hi, I just returned to P3.1 (from p6) and am struggling with getting the Planned Percent Complete for activities from the target schedule. I’m trying to do it in gantt chart view, and then summarise.

Is there an easy way?

3 replies

Oldest first
  1. 0
    Paul Harris ·
    I usually autostatus using progress spotlight a copy of the baseline and set it as Target 2. The % complete of this schedule will be the planned % complete.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
    www.eh.com.au


  2. 0
    Paul Harris ·
    I usually autostatus using progress spotlight a copy of the baseline and set it as Target 2. The % complete of this schedule will be the planned % complete.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
    www.eh.com.au


  3. 0
    Gavin Morris ·
    Thanks Paul, that’ll do for me. Easy when you know how ... :)