Budgeted Quantity

Mohammed MujtabaMember for 18 years 2 months
Created
1
10
0
Dear Planners,

After loading the budgeted quantity (manhours), when i add up all the manhours, it is not matching with the manhours in the primavera p3. How to get the exact mhrs in the loading.

1 reply

Oldest first
  1. 0
    Sajid Balma ·
    You might have multiple resources assigned to various activities. P3 calculates/adds up the budgeted quantity regardless of their unit. So like if you have 600 cum of concrete and 900 mhr on an activity. P3 will give u a budgeted quantity as 1500.

    If you need to make sure that the BQ of mhr and your arthimatic sum is same, run a resource tabular/graphic report on your mhr resource id.

Log in or join to reply