Budgeted Qty

Mohammed MujtabaMember for 18 years 1 month
Created
1
1
0
Dear planners,

Recently i made a recovery schedule with some addition of budgeted wty (manhours)but eventhough i have run the global change, the budg qty(mhrs)which i have added is not considered.
AND
In the loading also the budg qty is not matching.

Pls suggest ...

1 reply

Oldest first
  1. 0
    Arnold Puy ·
    Hi Mohammed,

    The best way of loading or adding Budgeted Quantity is to export to Excel, it is more accurate rather than using Global Change it is uncertain.

    Arnold

Log in or join to reply