Resource Hammock
- Created
- 12
- 4
I am trying to automatically create several hammocks whose start will be defined by early use of a given resource and its finish will be determined by the late finish of the resourceuse by its predecessors SS/FF. The resource FM1 TO FM10 will be allocated using skills and will vary when changes in duration of other activities occur.
I want to be able to model such variations automatically in a Monte Carlo simulation as to explore the cost probabilities. If using 9 Freezing Machines the deterministic cost will be less but the float availability will also be less, I suspect the option for 10 Freezing Machines will be a better choice.
FROM RESOURCE GANTT
FROM ACTIVITY GANTT
http://www.mediafire.com/download/xa4lqyo4ltxxt3d/RD601.009.sprj
http://www.mediafire.com/download/7tx1v31locf4ca6/RD601.010.sprj
Any ideas?
12 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?