Thermal & Moisture Protection
Subjects on this page
| Activity | Entry (verbatim) | Value | Source |
|---|---|---|---|
| Gravel Chippings | Roof Protections Gravel & Chippings - Allow a rate of 1.4 tonnes/day for transporting and laying out solar reflective chippings. | 1.4 t per dayper dayParsed | Gravel Chippings |
| P.V.C. Sheeting | P.V.C. Sheeting Usually carried out with a minimum of a 3 man gang with a labourer. Large Roof Areas = 50 m2/day Smaller Areas = 40 m2/day2 rate statements found; left for an editor | — | P.V.C. Sheeting |
| Polythene Waterproofing | Polythene Sheeting Sheet materials (DPC/DPM's etc) fixed to prepared concrete surfaces. Horizontal Surfaces = 20.0 m2/hr | 20 m2 per hrper hrParsed | Polythene Waterproofing |
1–3 of 3
These values were contributed by members and reflect the conditions, methods and regions they worked in. They are a starting point for estimating, not a standard. Check them against your own records, the site conditions and the contract before relying on them.