Mandatory Start Constraints
- Created
- 6
- 4
Hi All
A quick question on constraints in particular the dreaded mandatory Constraint.
FYI this is more of a hypothectical contractual question although something similar has happened on one of our contracts.
If a client requests a mandatory constraint to be used for an interim milestone in a schedule (which is not the start or finish) what affect will this have? I understand that these connstraints in a way affect the forward and backward pass computations and force a result on a schedule.
Would a contractor have any entitlement to remove this later?
Thanks in advance.
Aidan
6 replies
Oldest firstLog in or join to reply