Skip to content

Are non-work calendar days claimable?

Carlos AranaMember for 17 years 4 months
Created
2
4
0

So,

This contractor was working under a 6 day-workweek calendar (Stablished in the contract), but in the seventh day (say, the sunday when there were no one working at the place) a storm hit the place of the works and the 8th day the place was not available to be worked because it was flooded. It took that day to recover from the efects of the flooding.

The storm affected activities over the critical path, the question is: The affectation to the finish date is one day (the flooded day) or two days (The day when it was raining plus the flooded day) ?

What do you think?

2 replies

Oldest first
  1. 0
    Rafael Davila ·

    It depends on the change of

    It depends on the change of finish dates of your job, on the impact. If due to weather conditions the one day lost to rain on Monday delayed the job to finish instead of next Saturday to finish next Monday you got delayed by 2 calendar days. If the Monday was a holiday then finish of job is delayed to next Tuesday you got delayed by 3 calendar days.

    What if there is a resource conflict and the delay is even more?

    Some people ask Float, is it real? .. and they are  right. Many software cannot handle float under resource leveling, cannot handle float under multiple constraints but can figure out the correct finish date. Also negative float creates a lot of issues. Float have been prostituted by those who insist on basing the analysis using float instead of observing the effect.

    By no means I pretend to say float has no value, correct float shall be displayed always but the impact is better determined by running the model.

  2. 0
    Mike Testro ·

    Hi Carlos Rafael is correct -

    Hi Carlos

    Rafael is correct - non work days are claimable if a prior delay moves the task over a non work period.

    I have known this to be many months if a delay puts the work over an embargo period in the contract.

    Remember as well that the delay period is expressed in calendar days so if you have put in a task bar to represent the delay period make sure that it has a 24/7 calendar and the duration column shows elapsed of calendar days.

    Best regards

    Mike T.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?