| Activity | Entry (verbatim) | Source |
|---|---|---|
| Electrical System | Electrical SystemTask / DescriptionSlow Ave Fast Units Railway Station 1st Fix- 38.0 - wks Railway Station 2nd Fix- 16.0 - wks Railway Station T&C- 8.0 - wks Cable Installation, 1 cable laid in trench and protect- 6.2 - m/hr Cable Installation, 2 cable laid in trench and protect- 5.6 - m/hr Cable Installation, 5 cable laid in trench and protect- 4.3 - m/hr Cable Installation, 7 cable laid in trench and protect- 3.7 - m/hr Cable Installation, 8 cable laid in trench and protect- 3.5 - m/hr Cable Installation, 2 cable laid in trench and protect, 100mm dia- 1.8 - m/hr Cable Installation, 2 cable laid in trench and protect, 135mm dia- 1.6 - m/hr Cable Installation, 3 cable laid in trench and protect, 100mm dia- 1.0 1.5 m/hr Cable Installation, 6 cable laid in trench and protect, 100mm dia- 0.7 1.2 m/hr Cable Installation, 4 cable laid in trench and protect, 150mm dia0.7 1.2 3.1 m/hr Cable Installation, 36 cable laid in trench and protect, 100mm dia- 0.2 - m/hr Cable Installation, 10 cable laid in trench and protect, 100mm dia- 0.5 - m/hr Cable Installation, 1 cable laid in trench and protect, 300mm dia- 1.3 - m/hr3 rate statements found; left for an editor | Electrical System |
| Floating Track Slab | Pre-cast concrete blocks that support standard steel tracks. They are used to reduce noise and vibration as the pre-cast track slab blocks are placed on resin pads (4 no per unit), held in place by fixed side and end restraint blocks. Side restraints, 0.8 m long, 12 no/day = 9.6 m/day Resin pads, 10 no/day = 10.0 m/day FST Units, 5 no/day = 10.0 m/day The above rates were achieved with a 6 man team, but could have been be speeded up by 200 300 % if a works train was available to hoist the units into place. The above was done with a "A" frame and chain hoist.6 rate statements found; left for an editor | Floating Track Slab |
| Trackwork | Trackwork...Task / DescriptionSlow Ave Fast Units FST Floating Track Slab, side restraints9.6 - - m/day FST Floating Track Slab, resin pads10.2 - - m/day FST Floating Track Slab, slab units10.6 - - m/day PCBT - Pre-cast Concrete Block Track, in Bored Tunnels17.1 41.0 - m/day PCBT - Pre-cast Concrete Block Track, in Cut and Cover Tunnels- 35.0 - m/day PCBT - Pre-cast Concrete Block Track, in Station Tunnels- 35.0 - m/day IST - Isolated Slab Track, in Bored Tunnels- 20.0 - m/day IST - Isolated Slab Track, in Cut and Cover Tunnels- 34.0 - m/day IST - Isolated Slab Track, in Station- 29.0 - m/day FST - Floating Slab Track, in Station3.6 4.6 5.7 m/day Ballasted Track, in Mainline57.0 71.0 115.0 m/day Ballasted Track, in Depot- 28.0 - m/day Non-Ballasted Track, in Depot8.5 12.8 17.4 m/day Embedded / Paved Track, in Depot- 71.0 - m/day Heavy Maintenance / Train Wash Track, in Depot- 29.0 - m/day Maintenance Pit, in Depot- 52.0 - m/day Siding Trackwork, in Depot- 38.0 - m/day3 rate statements found; left for an editor | Trackwork |
| Transportation Power Supply | Power SupplyTask / DescriptionSlow Ave Fast Units AC Install 2 no Service transformers, 6 men- 12.0 - days AC Install 2 no Switchgear, 7 men- 12.0 - days AC Install Associated Trays and ladders, 3 men11.0 5.0 - days AC Cable Terminations in Tx and SWG Rooms, 3 men12.0 6.0 - days DC Install Insulated Flooring in DC Room, 1 men- 5.0 - days DC Install 1 set Rectifier Transformer and Rectifier, 7 men- 1.0 - days DC Install Switchgear, 7 men- 10.0 - days DC Primary Cable Terminations and Busduct, 18 men12.0 9.0 - days DC Secondary Cable Terminations and Connections, 9 men12.0 6.0 - days Trackside Cabling 33kV/Pilot Cables, 10 men2,100.0 - - m run/day Trackside Cabling Terminations, 6 men- 1.0 - days | Transportation Power Supply |
1–4 of 4
These values were contributed by members and reflect the conditions, methods and regions they worked in. They are a starting point for estimating, not a standard. Check them against your own records, the site conditions and the contract before relying on them.