Transportation Production Rates & Build Times:
9 entriesSource page: Transportation
Subjects on this page
| Activity | Entry (verbatim) | Value | Source |
|---|---|---|---|
| Cable Car | The 21 months duration for the 14km cable car project from the land available date is made up of the following activities:5 months lead time to the mast foundation contract before the cable car contractor can get access to the foundation for a 10 months installation works. The cable car contractor's installation is followed by the last 2 months of their overall 6 months testing and commissioning. This is then followed by a 4 months of Test & Trial Running. The 27 months programme of cable car's manufacturing, delivery, installation and test and commissioning is based on the extract of the supplier's programme. | — | Cable Car |
| Crane Grab Hoists & Cranes | Tender rates are often quoted as between 20 and 25 m3/hr. With adequate supervision and sufficient loose spoil material supplied to the crane drop area, these rates can easily be increased. Grabs mounted on crawler cranes, rates depend on... Depth of the spoil to be removed Operative supervision - breaks etc Management and availibility of lorries Efficiency and utlisation of banksmen Transport of spoil to crane drop area Down time of machinery and staff Clamshell Grab Mounted on a crawler crane... 2.0 m3 bucket (HK Cut & Cover Tunnels) 33 m3/hr 1.5 m3 per lift 2.9 mins per lift 2.5 m3 bucket (HK Station Box) 41 m3/hr 2.0 m3 per lift 3.1 mins per lift3 rate statements found; left for an editor | — | Crane Grab |
| Electrical SystemRailways | Electrical SystemTask / DescriptionSlow Ave Fast Units Railway Station 1st Fix- 38.0 - wks Railway Station 2nd Fix- 16.0 - wks Railway Station T&C- 8.0 - wks Cable Installation, 1 cable laid in trench and protect- 6.2 - m/hr Cable Installation, 2 cable laid in trench and protect- 5.6 - m/hr Cable Installation, 5 cable laid in trench and protect- 4.3 - m/hr Cable Installation, 7 cable laid in trench and protect- 3.7 - m/hr Cable Installation, 8 cable laid in trench and protect- 3.5 - m/hr Cable Installation, 2 cable laid in trench and protect, 100mm dia- 1.8 - m/hr Cable Installation, 2 cable laid in trench and protect, 135mm dia- 1.6 - m/hr Cable Installation, 3 cable laid in trench and protect, 100mm dia- 1.0 1.5 m/hr Cable Installation, 6 cable laid in trench and protect, 100mm dia- 0.7 1.2 m/hr Cable Installation, 4 cable laid in trench and protect, 150mm dia0.7 1.2 3.1 m/hr Cable Installation, 36 cable laid in trench and protect, 100mm dia- 0.2 - m/hr Cable Installation, 10 cable laid in trench and protect, 100mm dia- 0.5 - m/hr Cable Installation, 1 cable laid in trench and protect, 300mm dia- 1.3 - m/hr3 rate statements found; left for an editor | — | Electrical System |
| Equipment Conveying decksConveying Systems | Conveying decks may be used in a variety of industries, for example in airport baggage handling systems or cargo handling systems. | — | Equipment Conveying decks |
| Floating Track SlabRailways | Pre-cast concrete blocks that support standard steel tracks. They are used to reduce noise and vibration as the pre-cast track slab blocks are placed on resin pads (4 no per unit), held in place by fixed side and end restraint blocks. Side restraints, 0.8 m long, 12 no/day = 9.6 m/day Resin pads, 10 no/day = 10.0 m/day FST Units, 5 no/day = 10.0 m/day The above rates were achieved with a 6 man team, but could have been be speeded up by 200 300 % if a works train was available to hoist the units into place. The above was done with a "A" frame and chain hoist.6 rate statements found; left for an editor | — | Floating Track Slab |
| Hydraulic ExcavatorHoists & Cranes | Tractor with backactor, Massey Ferguson or JCB.3 has a 0.3 m3 bucket. Smaller 360 degree excavator has a 0.4 m3 bucket. JCB.6D, Liebherr 400, Hymak 580 or typical 360 degree machine has a 0.5 m3 bucket. 360 degree excavator machine has a 0.6 m3 bucket. Large 360 degree crawler backhoes have a 0.75 m3 bucket. | — | Hydraulic Excavator |
| Rail Grab Hoists & Cranes | Machine Rail Mounted Hydraulic Grab Rate of 30 - 50 m3 of sand per hour (dependant upon depth), with 1.5 m3 made (2.0 m3 bucket) with each machine lift. Giving a required lift rate of 2.4 mins. A rate of 37 m3/hr (per rig) was achieved on HK Station box excavation. This was achieved with inadequate supervision and and long breaks etc. The standard lift time was 3 mins. | 37 m3 per hrper hrParsed | Rail Grab |
| TrackworkRailways | Trackwork...Task / DescriptionSlow Ave Fast Units FST Floating Track Slab, side restraints9.6 - - m/day FST Floating Track Slab, resin pads10.2 - - m/day FST Floating Track Slab, slab units10.6 - - m/day PCBT - Pre-cast Concrete Block Track, in Bored Tunnels17.1 41.0 - m/day PCBT - Pre-cast Concrete Block Track, in Cut and Cover Tunnels- 35.0 - m/day PCBT - Pre-cast Concrete Block Track, in Station Tunnels- 35.0 - m/day IST - Isolated Slab Track, in Bored Tunnels- 20.0 - m/day IST - Isolated Slab Track, in Cut and Cover Tunnels- 34.0 - m/day IST - Isolated Slab Track, in Station- 29.0 - m/day FST - Floating Slab Track, in Station3.6 4.6 5.7 m/day Ballasted Track, in Mainline57.0 71.0 115.0 m/day Ballasted Track, in Depot- 28.0 - m/day Non-Ballasted Track, in Depot8.5 12.8 17.4 m/day Embedded / Paved Track, in Depot- 71.0 - m/day Heavy Maintenance / Train Wash Track, in Depot- 29.0 - m/day Maintenance Pit, in Depot- 52.0 - m/day Siding Trackwork, in Depot- 38.0 - m/day3 rate statements found; left for an editor | — | Trackwork |
| Transportation Power SupplyRailways | Power SupplyTask / DescriptionSlow Ave Fast Units AC Install 2 no Service transformers, 6 men- 12.0 - days AC Install 2 no Switchgear, 7 men- 12.0 - days AC Install Associated Trays and ladders, 3 men11.0 5.0 - days AC Cable Terminations in Tx and SWG Rooms, 3 men12.0 6.0 - days DC Install Insulated Flooring in DC Room, 1 men- 5.0 - days DC Install 1 set Rectifier Transformer and Rectifier, 7 men- 1.0 - days DC Install Switchgear, 7 men- 10.0 - days DC Primary Cable Terminations and Busduct, 18 men12.0 9.0 - days DC Secondary Cable Terminations and Connections, 9 men12.0 6.0 - days Trackside Cabling 33kV/Pilot Cables, 10 men2,100.0 - - m run/day Trackside Cabling Terminations, 6 men- 1.0 - days | — | Transportation Power Supply |
1–9 of 9
These values were contributed by members and reflect the conditions, methods and regions they worked in. They are a starting point for estimating, not a standard. Check them against your own records, the site conditions and the contract before relying on them.