Electrical System

Task / DescriptionSlow  Ave  Fast   Units
 Railway Station 1st Fix-  38.0 -   wks
 Railway Station 2nd Fix-  16.0 -   wks
 Railway Station T&C-  8.0 -   wks
 Cable Installation, 1 cable laid in trench and protect-  6.2 -   m/hr
 Cable Installation, 2 cable laid in trench and protect-  5.6 -   m/hr
 Cable Installation, 5 cable laid in trench and protect-  4.3 -   m/hr
 Cable Installation, 7 cable laid in trench and protect-  3.7 -   m/hr
 Cable Installation, 8 cable laid in trench and protect-  3.5 -   m/hr
 Cable Installation, 2 cable laid in trench and protect, 100mm dia-  1.8 -   m/hr
 Cable Installation, 2 cable laid in trench and protect, 135mm dia-  1.6 -   m/hr
 Cable Installation, 3 cable laid in trench and protect, 100mm dia-  1.0 1.5  m/hr
 Cable Installation, 6 cable laid in trench and protect, 100mm dia-  0.7 1.2  m/hr
 Cable Installation, 4 cable laid in trench and protect, 150mm dia0.7 1.2 3.1  m/hr
 Cable Installation, 36 cable laid in trench and protect, 100mm dia-  0.2 -   m/hr
 Cable Installation, 10 cable laid in trench and protect, 100mm dia-  0.5 -   m/hr
 Cable Installation, 1 cable laid in trench and protect, 300mm dia-  1.3 -   m/hr