Transportation Power Supply

Started by James Williams ·
Last updated
Updated
Views
7 views

This page is part of the Rates, Norms & Durations library.

Open the norms tables →

Power Supply

Task / DescriptionSlow  Ave  Fast   Units
 AC Install 2 no Service transformers, 6 men-  12.0 -   days
 AC Install 2 no Switchgear, 7 men-  12.0 -   days
 AC Install Associated Trays and ladders, 3 men11.0 5.0 -   days
 AC Cable Terminations in Tx and SWG Rooms, 3 men12.0 6.0 -   days
 DC Install Insulated Flooring in DC Room, 1 men-  5.0 -   days
 DC Install 1 set Rectifier Transformer and Rectifier, 7 men-  1.0 -   days
 DC Install Switchgear, 7 men-  10.0 -   days
 DC Primary Cable Terminations and Busduct, 18 men12.0 9.0 -   days
 DC Secondary Cable Terminations and Connections, 9 men12.0 6.0 -   days
 Trackside Cabling 33kV/Pilot Cables, 10 men2,100.0 -  -   m run/day
 Trackside Cabling Terminations, 6 men-  1.0 -   days