Rates, Norms & Durations
Transportation Power Supply
In the Open Standard
Started by James Williams ·
- Last updated
- Updated
- Views
- 7 views
This page is part of the Rates, Norms & Durations library.
Open the norms tables →Power Supply
| Task / Description | Slow | Ave | Fast | Units |
| AC Install 2 no Service transformers, 6 men | - | 12.0 | - | days |
| AC Install 2 no Switchgear, 7 men | - | 12.0 | - | days |
| AC Install Associated Trays and ladders, 3 men | 11.0 | 5.0 | - | days |
| AC Cable Terminations in Tx and SWG Rooms, 3 men | 12.0 | 6.0 | - | days |
| DC Install Insulated Flooring in DC Room, 1 men | - | 5.0 | - | days |
| DC Install 1 set Rectifier Transformer and Rectifier, 7 men | - | 1.0 | - | days |
| DC Install Switchgear, 7 men | - | 10.0 | - | days |
| DC Primary Cable Terminations and Busduct, 18 men | 12.0 | 9.0 | - | days |
| DC Secondary Cable Terminations and Connections, 9 men | 12.0 | 6.0 | - | days |
| Trackside Cabling 33kV/Pilot Cables, 10 men | 2,100.0 | - | - | m run/day |
| Trackside Cabling Terminations, 6 men | - | 1.0 | - | days |