Slip Forming

Concrete - Slip Forming A typical period of 10 - 14 days is required to setup the shutter on the ground and cast the platform. Rate of climb of formwork = 200 - 300 mm/hr.
Slip Forming entries
ActivityEntry (verbatim)Source
Table FormsConcrete - Table Forms Fast method of forming walls/slabs with movable shutter. This rate is inclusive of walls and columns etc. Rate of 100 - 150 m2/dayTable Forms

1–1 of 1

These values were contributed by members and reflect the conditions, methods and regions they worked in. They are a starting point for estimating, not a standard. Check them against your own records, the site conditions and the contract before relying on them.