Rates, Norms & Durations
Slip Forming
In the Open Standard
Concrete - Slip Forming A typical period of 10 - 14 days is required to setup the shutter on the ground and cast the platform. Rate of climb of formwork = 200 - 300 mm/hr.
Started by Technical Development ·
- Last updated
- Updated
- Views
- 8 views
This page is part of the Rates, Norms & Durations library.
Open the norms tables →Concrete - Slip Forming
A typical period of 10 - 14 days is required to setup the shutter on the ground and cast the platform.
Rate of climb of formwork = 200 - 300 mm/hr.