Rates, Norms & Durations / Building & Construction / Roofs & Waterproofing
Tiled Roofs
Slates and TilingTask / DescriptionSlow Ave Fast Units Slate Roofs, Welsh Slate 3-5mm- 18.0 - m2/day Slate Roofs, Cumbrian Slate 8-11mm- 8.5 - m2/day Slate Roofs, Asbestos Slates- 36.0 - m2/day Tiled Roofs, Concrete Tiles- 52.0 - m2/day Tiled Roofs, Clay Pan Tiles- 26.0 - m2/day
2 entriesSource page: Tiled Roofs
Subjects on this page
| Activity | Entry (verbatim) | Source |
|---|---|---|
| Slate Roofs | Slate Roofs Usually carried out with a 2 man gang, sometimes with an additional labourer. Natural Welsh Slate 3.5-5 mm thick 18.0 m2/day Natural Cumbrian 8-11 mm thick 8.5 m2/day Asbestos Slates 36.0 m2/day3 rate statements found; left for an editor | Slate Roofs |
| Tiled Roofs | Usually carried out with a 2 man gang with 1 labourer. The rates include for felting, battening and fixing of tiles etc. Concrete Interlocking Tiles 52 m2/day Clay Pan Tiles 26 m2/day2 rate statements found; left for an editor | Tiled Roofs |
1–2 of 2
These values were contributed by members and reflect the conditions, methods and regions they worked in. They are a starting point for estimating, not a standard. Check them against your own records, the site conditions and the contract before relying on them.