Rates, Norms & Durations
Slate Roofs
In the Open Standard
Slate Roofs Usually carried out with a 2 man gang, sometimes with an additional labourer. Natural Welsh Slate 3.5-5 mm thick 18.0 m2/day
Started by admin ·
- Last updated
- Updated
- Views
- 9 views
This page is part of the Rates, Norms & Durations library.
Open the norms tables →Slate Roofs
Usually carried out with a 2 man gang, sometimes with an additional labourer.
|
Natural Welsh Slate |
3.5-5 mm thick |
18.0 m2/day |
|
Natural Cumbrian |
8-11 mm thick |
8.5 m2/day |
|
Asbestos Slates |
|
36.0 m2/day |