Tiled Roofs

Started by admin ·
Last updated
Updated
Views
9 views

This page is part of the Rates, Norms & Durations library.

Open the norms tables →

Slates and Tiling

Task / DescriptionSlow  Ave  Fast   Units
 Slate Roofs, Welsh Slate 3-5mm-  18.0 -   m2/day
 Slate Roofs, Cumbrian Slate 8-11mm-  8.5 -   m2/day
 Slate Roofs, Asbestos Slates-  36.0 -   m2/day
 Tiled Roofs, Concrete Tiles-  52.0 -   m2/day
 Tiled Roofs, Clay Pan Tiles-  26.0 -   m2/day