Trench Excavations

Trench Excavation...Task / DescriptionSlow Ave Fast Units Hydraulic Excavator, 0.3m3 bucket, Sand/Soil5.6 7.1 8.2 m3/hr Hydraulic Excavator, 0.3m3 bucket, Gravel Beds4.8 6.1 7.3 m3/hr Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk4.8 6.1 7.1 m3/hr Hydraulic Excavator, 0.3m3 bucket, Hard Ground9.7 5.4 6.4 m3/hr Hydraulic Excavator, 0.4m3 bucket, Sand/Soil20.5 25.0 29.2 m3/hr Hydraulic Excavator, 0.4m3 bucket, Gravel Beds18.2 22.2 26.0 m3/hr Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk18.2 22.2 26.0 m3/hr Hydraulic Excavator, 0.4m3 bucket, Hard Ground17.0 20.0 23.4 m3/hr Hydraulic Excavator, 0.5m3 bucket, Sand/Soil26.0 28.6 33.1 m3/hr Hydraulic Excavator, 0.5m3 bucket, Gravel Beds26.3 28.6 33.2 m3/hr Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk26.3 28.6 33.2 m3/hr Hydraulic Excavator, 0.5m3 bucket, Hard Ground22.7 25.0 28.8 m3/hr Excavate and Board Trench, 0.5-1.5m deep, < 2.0m wide3.3 4.5 6.8 m2/hr Excavate and Board Trench, 1.5-3.0m deep, < 2.0m wide3.0 4.2 6.5 m2/hr Excavate and Boar
Trench Excavations entries
ActivityEntry (verbatim)Source
Traditional mass fill foundationsIncludes excavation and concrete pour.Assumes 450mm wide, average of 1.5m deep, No earthwork support, reinforcement or claymaster.35 linear metres per day per gang.Traditional mass fill foundations

1–1 of 1

These values were contributed by members and reflect the conditions, methods and regions they worked in. They are a starting point for estimating, not a standard. Check them against your own records, the site conditions and the contract before relying on them.