Rates, Norms & Durations
Traditional mass fill foundations
In the Open Standard
Includes excavation and concrete pour.Assumes 450mm wide, average of 1.5m deep, No earthwork support, reinforcement or claymaster.35 linear metres per day per gang.
Started by Jason French ·
- Last updated
- Updated
- Views
- 9 views
This page is part of the Rates, Norms & Durations library.
Open the norms tables →Includes excavation and concrete pour.
Assumes 450mm wide, average of 1.5m deep, No earthwork support, reinforcement or claymaster.
35 linear metres per day per gang.