Trench Excavations

Started by admin ·
Last updated
Updated
Views
11 views

This page is part of the Rates, Norms & Durations library.

Open the norms tables →

Trench Excavation...

Task / DescriptionSlow  Ave  Fast   Units
 Hydraulic Excavator, 0.3m3 bucket, Sand/Soil5.6 7.1 8.2  m3/hr
 Hydraulic Excavator, 0.3m3 bucket, Gravel Beds4.8 6.1 7.3  m3/hr
 Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk4.8 6.1 7.1  m3/hr
 Hydraulic Excavator, 0.3m3 bucket, Hard Ground9.7 5.4 6.4  m3/hr
 Hydraulic Excavator, 0.4m3 bucket, Sand/Soil20.5 25.0 29.2  m3/hr
 Hydraulic Excavator, 0.4m3 bucket, Gravel Beds18.2 22.2 26.0  m3/hr
 Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk18.2 22.2 26.0  m3/hr
 Hydraulic Excavator, 0.4m3 bucket, Hard Ground17.0 20.0 23.4  m3/hr
 Hydraulic Excavator, 0.5m3 bucket, Sand/Soil26.0 28.6 33.1  m3/hr
 Hydraulic Excavator, 0.5m3 bucket, Gravel Beds26.3 28.6 33.2  m3/hr
 Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk26.3 28.6 33.2  m3/hr
 Hydraulic Excavator, 0.5m3 bucket, Hard Ground22.7 25.0 28.8  m3/hr
 Excavate and Board Trench, 0.5-1.5m deep, < 2.0m wide3.3 4.5 6.8  m2/hr
 Excavate and Board Trench, 1.5-3.0m deep, < 2.0m wide3.0 4.2 6.5  m2/hr
 Excavate and Board Trench, 3.0-4.5m deep, < 2.0m wide2.7 4.0 6.0  m2/hr
 Excavate and Board Trench, 0.5-1.5m deep, > 2.0m wide6.6 7.1 8.8  m2/hr
 Excavate and Board Trench, 1.5-3.0m deep, > 2.0m wide6.2 6.7 9.2  m2/hr
 Excavate and Board Trench, 3.0-4.5m deep, > 2.0m wide5.8 6.2 10.5  m2/hr