Open Standard · M2 Planning & Scheduling
M2.1 Planning & Schedule Development
Knowledge
Articles and chapters
- M2.2 — Logic, Critical Path & Float21 Oct 2026
The learner should be able to construct and analyse a logically linked schedule, choose relationships, recognise missing or inappropriate logic, distinguish logic from constraints, identify critical and near-critical paths, understand total and free float, recognise negative or unusually high float.
- M1.2 — Coding & Control Structures21 Oct 2026
By the end of this section, the practitioner should be able to design and apply a coherent set of coding and control structures that allows project information to be organised, integrated, aggregated, reconciled and reported without repeatedly rebuilding the underlying data.
- M1.3 — Integrated Baselines21 Oct 2026
By the end of this section, the practitioner should be able to establish, test and explain an integrated project baseline that brings authorised scope, schedule, budget, assumptions, progress rules and accountability into one coherent reference position.
- M1.5 — Data Quality, Integration & Traceability21 Oct 2026
By the end of this section, the learner should be able to establish and operate a project-controls data environment in which important information is complete enough, accurate enough, timely enough, consistent enough and traceable enough to support management decisions.
- M2.1 — Planning & Schedule Development21 Oct 2026
By the end of this section, the learner should be able to turn authorised scope and an agreed delivery strategy into a credible, structured and maintainable project schedule that explains what work must be performed, in what broad sequence, and over what durations and calendars etc.
- M1.1 — Scope & Work Breakdown Structures21 Oct 2026
By the end of this section, the practitioner should be able to take an authorised project scope and turn it into a Work Breakdown Structure.
- M1.4 — Progress Measurement21 Oct 2026
By the end of this section, the learner should be able to design, apply and challenge progress-measurement rules that convert evidence of completed work into a credible statement of physical accomplishment. They should be able to choose an appropriate measurement method.
- M6.5 — Claims & Forensic Analysis20 Oct 2026
1. Practical outcome The learner should be able to preserve relevant records, define a forensic question, establish a reliable chronology, test cause and effect across schedule and cost, distinguish facts from assumptions and produce reproducible findings. They should understand how project-controls…
- Project Controls Open Standard17 Oct 2026
Collaborative work -n-progress contributed by members and experts from across the community cadre.The Project Controls Open Standard brings together practical project controls knowledge in one free,…
- M6.3 — Baseline Change & Configuration Control17 Oct 2026
1. Practical outcomeThe learner should be able to turn a bounded approval into a verified revision of the affected scope, schedule, budget, progress, risk and configuration records. They should preserve previous baselines, maintain relationships between approved, forecast and as-built information,…
Discussions
16,275 discussions
- 1replyActual Finish Dates On Team MemberOracle Primavera - PM6by Steve Shunk· 7 years ago
- 5repliesEngineering SequencingPlanning, Scheduling & Programming Discussionby Eric Gonzalez· 7 years ago
- 4repliesProject Summary Task Displaying Inaccurate Total SlackMicrosoft Projectby Brian Bennett· 7 years ago
- 3repliesCritical bars Display before BaselineOracle Primavera - PM6by Muhammad Saqib· 7 years ago
- 4repliesPage Setup, Paper Size showing only 2 optionsOracle Primavera - PM6by Muhammad Saqib· 7 years ago
- 2repliesPS8 vs PSNext vs SciformaSciformaby Alexandre Faulx-Briole· 7 years ago
- 2repliesSo why does Oracle Primavera still not compute Critical Path Drag?Oracle Primavera - PM6by Stephen Devaux· 7 years ago
- 7repliesActivity duration changedOracle Primavera - PM6by Hamid Tavassoli· 7 years ago
- 2repliesPrimavera Layout - Information fetchOracle Primavera - PM6by Pulkit Verma· 7 years ago
- 1replyP6 Interview TestOracle Primavera - PM6by Simon Carter· 7 years ago
1,201–1,210 of 16,275
Blogs
Thought leadership
- How Project Planners Should Deal with a Difficult Client PMO17 Oct 2026
Ten ways to keep your client happy, protect your construction programme and build stronger working relationships.Every construction planner knows that keeping the client happy matters. But what…
Sunchana Johnston
- PROCEDURES No 16 – Quality Standards23 Aug 2026
Fed up with adverts from software companies and consultancies that are going to change the world of Planning and solve all your project problems? This series of occasional articles promises nothing but thought provoking questions on how well we understand the basics of our profession from the…
PP Admin
- Sunchana’s P6 Lancelot Meets OPC Star Wars10 Aug 2026
Several months ago, I was engaged as the planning lead with one of the most significant infrastructure organisations.My assignments appeared straightforward: to provide independent planning expertise and advise senior stakeholders on the most appropriate software solution to support the extensive…
Sunchana Johnston
- PROCEDURES No 15 – Planning Standards10 Aug 2026
Fed up with adverts from software companies and consultancies that are going to change the world of Planning and solve all your project problems? This series of occasional articles promises nothing but thought provoking questions on how well we understand the basics of our profession from the…
PP Admin
- Programme Planning Standards: The Rules of the Game5 Jul 2026
Programme Planning Standards: The Rules of the GameStudies consistently show that organisations with mature project management practices achieve better delivery outcomes than those with ad hoc approaches. Yet one of the simplest disciplines is often overlooked—agreeing a common Programme Planning…
Sunchana Johnston
- Work = Life Priorities4 Dec 2020
Balancing our work and home lives is a challenge that nearly everyone faces. I was a single parent for many years and managed large teams and projects in Fortune 100 companies. It was not always easy. Recently, I was talking to an old friend and former colleague. When we worked together, she did not
Alan Zucker
Jobs
Roles asking for this
- ManchesterPermanent EmploymentCivil / Building / E&M£100-130,000
- MacclesfieldPermanent EmploymentCivil / Building / E&M£95,000
- LondonPermanent EmploymentTBC
- LondonPermanent EmploymentCivil / Building / E&M£120,000
Norms & Rates
Rates, norms and durations
| Activity | Entry (verbatim) | Section | Source |
|---|---|---|---|
| 005 Initiate Phase | IT Engineering Projects | 005 Initiate Phase | |
| 010 Analyse Phase | IT Engineering Projects | 010 Analyse Phase | |
| 015 Design Phase | IT Engineering Projects | 015 Design Phase | |
| 020 Develop Phase | IT Engineering Projects | 020 Develop Phase | |
| 025 Test Phase | IT Engineering Projects | 025 Test Phase | |
| 030 Implement Phase | IT Engineering Projects | 030 Implement Phase | |
| 035 Support Phase | IT Engineering Projects | 035 Support Phase | |
| Aluminium Roofing | Aluminium Roofing Metal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc. Flat Roof Aluminium Work = 2.8 m2/day Sloping Roof Aluminium Work = 1.9 m2/day | Metal Roof Decking | Aluminium Roofing |
Resources
Papers, standards and tools
No resources yet
Summaries of papers, standards and tools are added by editors and appear here once published.