Metal Roof Decking
7 entriesSource page: Metal Roof Decking
Subjects on this page
| Activity | Entry (verbatim) | Value | Source |
|---|---|---|---|
| Aluminium Roofing | Aluminium Roofing Metal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc. Flat Roof Aluminium Work = 2.8 m2/day Sloping Roof Aluminium Work = 1.9 m2/day2 rate statements found; left for an editor | — | Aluminium Roofing |
| Copper Roofing | Metal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc. Copper Roofing Flat Roof Copper Work = 3.0 m2/day Sloping Roof Copper Work = 2.7 m2/day2 rate statements found; left for an editor | — | Copper Roofing |
| Lead Roofing | Metal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc. Lead Roofing Flat Roof Lead Work = 2.5 m2/day Sloping Roof Lead Work = 2.1 m2/day2 rate statements found; left for an editor | — | Lead Roofing |
| Metal Decking | Metal Decking SystemsUsually carried out with a minimum of a 3 man gang with a labourer.Large Roof Areas = 70 m2/daySmaller or Complicated Areas = 28 m2/dayMetal DeckingTask / DescriptionSlow Ave Fast Units Metal Decking, large areas- 70.0 - m2/day Metal Decking, small or complicated- 28.0 - m2/day Titanium Sheeted Roofs- 9.5 - m2/day Copper Roofs, flat work- 3.0 - m2/day Copper Roofs, sloping work- 2.7 - m2/day Zinc Roofs, flat work- 2.4 - m2/day Zinc Roofs, sloping work- 2.1 - m2/day Aluminium Roofs, flat work- 2.8 - m2/day Aluminium Roofs, sloping work- 1.9 - m2/day Lead Roofs, flat work- 2.5 - m2/day Lead Roofs, sloping work- 2.1 - m2/day Lead Roofs, dormer cheeks- 1.3 - m2/day Lead Roofs, flat gutters- 88.0 - m/day Lead Roofs, flat copings- 76.0 - m/day Lead Roofs, stepped gutters- 3.5 - m/day Lead Roofs, shaped copings- 3.3 - m/day Lead Roofs, cover step flashings- 3.2 - m/day Lead Roofs, rooflight flashings- 0.8 - no/day Lead Roofs, domed roof coverings- 0.7 - m2/day2 rate statements found; left for an editor | — | Metal Decking |
| Metal Features | Metal Roof Features Composite rates have been calculated to provide an approximation of the time elements for these ancillary parts to metal roofs. Dormer Cheeks 1.36 m2/day Flat Gutter & Coping Flashings negligible time Step Gutter & Shaped Copings 3.50 m/day Cover Step Flashings 3.20 m/day Roof Light Flashing 0.80 no/day Dome Structures 0.75 m2/day5 rate statements found; left for an editor | — | Metal Features |
| Titanium Roofing | Titanium Roofing System Metal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc. Titanium roof on multiple sub‑layers. Typical composite rate of 9.5 m2/day. Installation Typical timing and sequence of works. This is for an order of 5,000 m2 (HK Station Upper & Lower Roofs)... Element Week Manpower Temporary Works 0 - 2 5 Metal Decking 2 - 3 12 Gutter Subframe 3 - 6 6 Vapour Barrier 4 - 13 4 Rockwool 4 – 13 44 Cement Board 4 – 13 6 Ice / Water Shield 4 – 13 4 Gutter Lining 6 - 9 4 Aluminium Cladding / Subframe 6 – 11 6 Titanium Cladding 8 – 17 17 Aluminium Pannelling 9 - 14 6 | 9.5 m2 per dayper dayParsed | Titanium Roofing |
| Zinc Roofing | Zinc Roofing Metal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc. Flat Roof Zinc Work = 2.3 m2/day Sloping Roof Zinc Work = 1.9 m2/day2 rate statements found; left for an editor | — | Zinc Roofing |
1–7 of 7
These values were contributed by members and reflect the conditions, methods and regions they worked in. They are a starting point for estimating, not a standard. Check them against your own records, the site conditions and the contract before relying on them.