How does Primavera P6 calculate Planned Value Cost for Activities without linear distribution (using Resource Curves or Manual plan) in Earned Value Management

When we use Earned Value Management technique, we focus on:Planned Value Cost (PV) = Budget At Completion * Schedule % CompleteEarned Value Cost (EV) = Budget At Completion * Performance % Complete (usually equal to Activity % Complete)Schedule Variance (SV) = EV - PVSV > 0 : project is good, ahead

17 Feb 2018 · Khuong Do · 2 min read