Metal Features
In the Open Standard
Metal Roof Features Composite rates have been calculated to provide an approximation of the time elements for these ancillary parts to metal roofs. Dormer Cheeks 1.36 m2/day Flat Gutter & Coping Flashings
Started by admin ·
- Last updated
- Updated
- Views
- 9 views
This page is part of the Rates, Norms & Durations library.
Open the norms tables →Metal Roof Features
Composite rates have been calculated to provide an approximation of the time elements for these ancillary parts to metal roofs.
|
Dormer Cheeks |
1.36 m2/day |
|
Flat Gutter & Coping Flashings |
negligible time |
|
Step Gutter & Shaped Copings |
3.50 m/day |
|
Cover Step Flashings |
3.20 m/day |
|
Roof Light Flashing |
0.80 no/day |
|
Dome Structures |
0.75 m2/day |