Rates, Norms & Durations
Lead Roofing
In the Open Standard
Started by admin ·
- Last updated
- Updated
- Views
- 9 views
This page is part of the Rates, Norms & Durations library.
Open the norms tables →Metal roof works are usually carried out with 2 men gangs of skilled labour.
The rates do not include for the timber backing structures etc.
Lead Roofing Flat Roof Lead Work = 2.5 m2/day
Sloping Roof Lead Work = 2.1 m2/day