Titanium Roofing System Metal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc. Titanium roof on multiple sub‑layers. Typical composite rate of 9.5 m2/day. Installation
- Last updated
- Updated
- Views
- 9 views
This page is part of the Rates, Norms & Durations library.
Open the norms tables →Titanium Roofing System
Metal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc.
Titanium roof on multiple sub‑layers.
Typical composite rate of 9.5 m2/day.
Installation
Typical timing and sequence of works. This is for an order of 5,000 m2 (HK Station Upper & Lower Roofs)...
|
Element |
Week |
Manpower |
|
Temporary Works |
0 - 2 |
5 |
|
Metal Decking |
2 - 3 |
12 |
|
Gutter Subframe |
3 - 6 |
6 |
|
Vapour Barrier |
4 - 13 |
4 |
|
Rockwool |
4 – 13 |
44 |
|
Cement Board |
4 – 13 |
6 |
|
Ice / Water Shield |
4 – 13 |
4 |
|
Gutter Lining |
6 - 9 |
4 |
|
Aluminium Cladding / Subframe |
6 – 11 |
6 |
|
Titanium Cladding |
8 – 17 |
17 |
|
Aluminium Pannelling |
9 - 14 |
6 |