Open Standard · M2 Planning & Scheduling
Schedule development
Knowledge
Articles and chapters
- M2.2 — Logic, Critical Path & Float21 Oct 2026
The learner should be able to construct and analyse a logically linked schedule, choose relationships, recognise missing or inappropriate logic, distinguish logic from constraints, identify critical and near-critical paths, understand total and free float, recognise negative or unusually high float.
- M1.2 — Coding & Control Structures21 Oct 2026
By the end of this section, the practitioner should be able to design and apply a coherent set of coding and control structures that allows project information to be organised, integrated, aggregated, reconciled and reported without repeatedly rebuilding the underlying data.
- M1.3 — Integrated Baselines21 Oct 2026
By the end of this section, the practitioner should be able to establish, test and explain an integrated project baseline that brings authorised scope, schedule, budget, assumptions, progress rules and accountability into one coherent reference position.
- M1.5 — Data Quality, Integration & Traceability21 Oct 2026
By the end of this section, the learner should be able to establish and operate a project-controls data environment in which important information is complete enough, accurate enough, timely enough, consistent enough and traceable enough to support management decisions.
- M2.1 — Planning & Schedule Development21 Oct 2026
By the end of this section, the learner should be able to turn authorised scope and an agreed delivery strategy into a credible, structured and maintainable project schedule that explains what work must be performed, in what broad sequence, and over what durations and calendars etc.
- M1.1 — Scope & Work Breakdown Structures21 Oct 2026
By the end of this section, the practitioner should be able to take an authorised project scope and turn it into a Work Breakdown Structure.
- M1.4 — Progress Measurement21 Oct 2026
By the end of this section, the learner should be able to design, apply and challenge progress-measurement rules that convert evidence of completed work into a credible statement of physical accomplishment. They should be able to choose an appropriate measurement method.
- M6.5 — Claims & Forensic Analysis20 Oct 2026
1. Practical outcome The learner should be able to preserve relevant records, define a forensic question, establish a reliable chronology, test cause and effect across schedule and cost, distinguish facts from assumptions and produce reproducible findings. They should understand how project-controls…
- Project Controls Open Standard17 Oct 2026
Collaborative work -n-progress contributed by members and experts from across the community cadre.The Project Controls Open Standard brings together practical project controls knowledge in one free,…
- M6.3 — Baseline Change & Configuration Control17 Oct 2026
1. Practical outcomeThe learner should be able to turn a bounded approval into a verified revision of the affected scope, schedule, budget, progress, risk and configuration records. They should preserve previous baselines, maintain relationships between approved, forecast and as-built information,…
Discussions
4,588 discussions
- 5repliesExample in turnarounds for 4 basic relationships.Shutdowns / Turnarounds / Outages (STOs)by Floris Gering· 12 years ago
- 5repliesPLEASE HELP ME HOW TO REDUCE THE FLOAT IN P6Planning, Scheduling & Programming Discussionby Fareed Memon· 12 years ago
- 5repliesProblems in getting updatesPlanning, Scheduling & Programming Discussionby Changli Wang· 12 years ago
- 5repliesA Pipeline ProjectPlanning, Scheduling & Programming Discussionby Nithin Raju· 12 years ago
- 5repliesAdtivity Duration and resource levellingPlanning, Scheduling & Programming Discussionby Nikan G· 12 years ago
- 5repliesSuccessors calapse when manually starting or completing a predecessorPlanning, Scheduling & Programming Discussionby Charlie Daniels· 12 years ago
- 5repliesProcurement ProblemPlanning, Scheduling & Programming Discussionby Moutaz Aldeib· 12 years ago
- 5repliesScheduling Best Practice ConundrumsPlanning, Scheduling & Programming Discussionby Emily Foster· 12 years ago
- 5repliesSimple manpower planning software.Planning, Scheduling & Programming Discussionby Neil Graham· 12 years ago
- 5repliesInterview Question for the Planning EngineerPlanning, Scheduling & Programming Discussionby Nouman Zia· 13 years ago
1,221–1,230 of 4,588
Blogs
Thought leadership
- How Project Planners Should Deal with a Difficult Client PMO17 Oct 2026
Ten ways to keep your client happy, protect your construction programme and build stronger working relationships.Every construction planner knows that keeping the client happy matters. But what…
Sunchana Johnston
- PROCEDURES No 16 – Quality Standards23 Aug 2026
Fed up with adverts from software companies and consultancies that are going to change the world of Planning and solve all your project problems? This series of occasional articles promises nothing but thought provoking questions on how well we understand the basics of our profession from the…
PP Admin
- Sunchana’s P6 Lancelot Meets OPC Star Wars10 Aug 2026
Several months ago, I was engaged as the planning lead with one of the most significant infrastructure organisations.My assignments appeared straightforward: to provide independent planning expertise and advise senior stakeholders on the most appropriate software solution to support the extensive…
Sunchana Johnston
- Programme Planning Standards: The Rules of the Game5 Jul 2026
Programme Planning Standards: The Rules of the GameStudies consistently show that organisations with mature project management practices achieve better delivery outcomes than those with ad hoc approaches. Yet one of the simplest disciplines is often overlooked—agreeing a common Programme Planning…
Sunchana Johnston
- Work = Life Priorities4 Dec 2020
Balancing our work and home lives is a challenge that nearly everyone faces. I was a single parent for many years and managed large teams and projects in Fortune 100 companies. It was not always easy. Recently, I was talking to an old friend and former colleague. When we worked together, she did not
Alan Zucker
- Your Plan is wrong3 Dec 2018
It is wrong from the moment you print it on paper. This is true in all aspects of life, as life happens every minute, and there are always things that you couldn’t possibly be aware of before you finalize your plan.Still, the first step of any project is to create a Plan. You’ll be asked to create…
Abbas Shakourifar
Jobs
Roles asking for this
- ManchesterPermanent EmploymentCivil / Building / E&M£100-130,000
- MacclesfieldPermanent EmploymentCivil / Building / E&M£95,000
- LondonPermanent EmploymentTBC
- LondonPermanent EmploymentCivil / Building / E&M£120,000
Norms & Rates
Rates, norms and durations
| Activity | Entry (verbatim) | Section | Source |
|---|---|---|---|
| 005 Initiate Phase | IT Engineering Projects | 005 Initiate Phase | |
| 010 Analyse Phase | IT Engineering Projects | 010 Analyse Phase | |
| 015 Design Phase | IT Engineering Projects | 015 Design Phase | |
| 020 Develop Phase | IT Engineering Projects | 020 Develop Phase | |
| 025 Test Phase | IT Engineering Projects | 025 Test Phase | |
| 030 Implement Phase | IT Engineering Projects | 030 Implement Phase | |
| 035 Support Phase | IT Engineering Projects | 035 Support Phase | |
| Aluminium Roofing | Aluminium Roofing Metal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc. Flat Roof Aluminium Work = 2.8 m2/day Sloping Roof Aluminium Work = 1.9 m2/day | Metal Roof Decking | Aluminium Roofing |
Resources
Papers, standards and tools
No resources yet
Summaries of papers, standards and tools are added by editors and appear here once published.