Skip to content
Rates, Norms & Durations

Cable Car

The 21 months duration for the 14km cable car project from the land available date is made up of the following activities:

Started by admin ·
Last updated
Updated
Views
12 views

This page is part of the Rates, Norms & Durations library.

Open the norms tables →

The 21 months duration for the 14km cable car project from the land available date is made up of the following activities:

  • 5 months lead time to the mast foundation contract before the cable car contractor can get access to the foundation for a 10 months installation works.
  • The cable car contractor's installation is followed by the last 2 months of their overall 6 months testing and commissioning.
  • This is then followed by a 4 months of Test & Trial Running. 

The 27 months programme of cable car's manufacturing, delivery, installation and test and commissioning is based on the extract of the supplier's programme.

Comments

No comments yet.

Log in or join to comment