Crane Grab
In the Open Standard
Started by Technical Development ·
- Last updated
- Updated
- Views
- 8 views
This page is part of the Rates, Norms & Durations library.
Open the norms tables →Tender rates are often quoted as between 20 and 25 m3/hr. With adequate supervision and sufficient loose spoil material supplied to the crane drop area, these rates can easily be increased. Grabs mounted on crawler cranes, rates depend on...
- Depth of the spoil to be removed
- Operative supervision - breaks etc
- Management and availibility of lorries
- Efficiency and utlisation of banksmen
- Transport of spoil to crane drop area
- Down time of machinery and staff
Clamshell Grab Mounted on a crawler crane... 2.0 m3 bucket (HK Cut & Cover Tunnels)
- 33 m3/hr
- 1.5 m3 per lift
- 2.9 mins per lift
2.5 m3 bucket (HK Station Box)
- 41 m3/hr
- 2.0 m3 per lift
- 3.1 mins per lift