Schedule Variance

Started by Technical Development ·
Last updated
Updated
Views
13 views

A parameter of [[Earned Value Analysis]]. The difference between the [[Budgeted Cost]] of work carried out and the budgeted cost of work planned.

The difference between the planned performance and actual performance.

The difference between identical activities or milestones (typically the project completion milestone) in the [[current schedule]] and in the [[baseline schedule]].