Progress Override

Started by Technical Development ·
Last updated
Updated
Views
10 views

A method of calculating the [[Critical Path]] in partially completed projects taking account of Out of Sequence Progress. Where activities have been progressed out of sequence, Predecessor dependencies are ignored.

See also [[Retained Logic]].