Progress Override
In the Open Standard
Started by Technical Development ·
- Last updated
- Updated
- Views
- 10 views
A method of calculating the [[Critical Path]] in partially completed projects taking account of Out of Sequence Progress. Where activities have been progressed out of sequence, Predecessor dependencies are ignored.
See also [[Retained Logic]].