Arrow Diagram Method
In the Open Standard
Started by Technical Development ·
- Last updated
- Updated
- Views
- 12 views
A network diagramming technique in which activities are represented by arrows.
The tail of the arrow represents the start and the head represents the finish of the activity (the length of the arrow does not represent the expected duration of the activity).
Activities are connected at points called nodes (usually drawn as small circles) to illustrate the sequence in which the activities are expected to be performed.
See also [[Precedence Diagram Method]].