Start-to-Finish
In the Open Standard
Started by Technical Development ·
- Last updated
- Updated
- Views
- 11 views
A relationship between two activities where the [[Successor]] activity (the second activity) cannot finish until the [[Predecessor]] activity (the first activity) has started.
This is essentially an illogical [[Dependency]] as it implies time running backwards, however, it is sometimes used to schedule the successor activity 'as late as possible' in relation to the predecessor activity.