Restrictions that affect the sequence or timing of an activity. These include predecessor dependencies but more often refer to Imposed Dates.
An imposed date restriction on the start or finish of an activity that overrides logic relationships.
Positioning an activity to start As Soon As Possible (ASAP) or As Late As Possible (ALAP) thus overiding available float.