What is needed to come up with a production rate?A duration of time, the manhours involved, and an amount of work produced?This section is here to document this. What information do you have that you can share?
Rates, Norms & Durations entries
ActivityEntry (verbatim)Source
Working PlatformsBuilding & ConstructionWorking PlatformsTask / DescriptionSlow Ave Fast Units Metal KwikStage, 5 Boards with 2m lifts11.1 11.9 12.5 m run/hr Metal KwikStage, 5 Boards with 3m lifts9.1 10.0 10.5 m run/hr Metal KwikStage, House Scaffold with 3 lifts2.8 3.2 3.8 m run/hr Metal Tube and Fittings, 5-6 Boards wide3.2 3.7 4.6 m run/hr Tube and Fitting Platforms, 50-250m310.6 12.5 18.5 m3/hr Tube and Fitting Platforms, 250-1000m318.5 22.5 24.5 m3/hr Tube and Fitting Platforms, over 1000m324.5 30.0 33.5 m3/hr Tube and Fitting Platforms, striking- 200.0 - % x erect3 rate statements found; left for an editorWorking Platforms
Zinc RoofingMetal Roof DeckingZinc Roofing Metal roof works are usually carried out with 2 men gangs of skilled labour. The rates do not include for the timber backing structures etc. Flat Roof Zinc Work = 2.3 m2/day Sloping Roof Zinc Work = 1.9 m2/day2 rate statements found; left for an editorZinc Roofing

201–202 of 202

These values were contributed by members and reflect the conditions, methods and regions they worked in. They are a starting point for estimating, not a standard. Check them against your own records, the site conditions and the contract before relying on them.