Working Platforms
Task / DescriptionSlow  Ave  Fast   Units
 Metal KwikStage, 5 Boards with 2m lifts11.1 11.9 12.5  m run/hr
 Metal KwikStage, 5 Boards with 3m lifts9.1 10.0 10.5  m run/hr
 Metal KwikStage, House Scaffold with 3 lifts2.8 3.2 3.8  m run/hr
 Metal Tube and Fittings, 5-6 Boards wide3.2 3.7 4.6  m run/hr
 Tube and Fitting Platforms, 50-250m310.6 12.5 18.5  m3/hr
 Tube and Fitting Platforms, 250-1000m318.5 22.5 24.5  m3/hr
 Tube and Fitting Platforms, over 1000m324.5 30.0 33.5  m3/hr
 Tube and Fitting Platforms, striking-  200.0 -   % x erect
 