Waterproofing

Task / DescriptionSlow Ave

Started by admin ·
Last updated
Updated
Views
8 views

This page is part of the Rates, Norms & Durations library.

Open the norms tables →
Task / DescriptionSlow  Ave  Fast   Units
 Asphalt coatings, horizontal surfaces3.5 4.2 5.8  m2/hr
 Asphalt coatings, vertical surfaces1.2 1.7 2.2  m2/hr
 Bituminous Brushed application, 2 coats4.8 5.0 6.3  m2/hr
 Bituminous Brushed application, 3 coats3.3 3.5 4.4  m2/hr
 Bituminous Sheets, horizontal surfaces3.8 4.0 4.8  m2/hr
 Bituminous Sheets, vertical surfaces3.3 3.5 4.2  m2/hr
 Polythene Sheets, horizontal surfaces-  20.0 -   m2/hr
 Bentonite Sheets, horizontal surfaces18.7 25.0 31.3  m2/hr
 Bentonite Sheets, vertical surfaces11.2 15.0 17.3  m2/hr
 Epoxy Based application, 1 coat-  75.0 -   m2/hr
 Epoxy Based application, 2 coat-  38.0 -   m2/hr