What is needed to come up with a production rate?A duration of time, the manhours involved, and an amount of work produced?This section is here to document this. What information do you have that you can share?
202 entriesSource page: Rates, Norms & Durations
Subjects on this page
| Activity | Entry (verbatim) | Value | Source |
|---|---|---|---|
| Cutting BackDemolition & Break Out | Cutting Back Concrete Cutting Piles For Pile Caps, Using Breaker & Air Tools Providing A Rough Finish (hrs/pile)Pile Diameter-->0.35m0.5m0.6m0.79m0.94m1.1m2.2m0 - 100mm high0.320.440.630.931.381.74 8.10100-200mm high0.390.560.811.221.832.16 8.58200-300mm high0.440.640.941.451.922.34 9.00300-500mm high0.490.721.071.652.102.50 9.50500-750mm high0.681.021.542.162.552.5510.01750-1000mm high0.831.321.782.363.374.2010.52 Providing A Neat Finish (hrs/pile)Pile Diameter-->0.35m0.5m0.6m0.79m0.94m1.1m2.2m0 - 100 mm high -0.630.901.321.932.25 9.72100-200 mm high -0.761.111.652.392.8110.29200-300 mm high -0.851.251.932.493.0410.85300-500 mm high -1.051.592.382.733.2511.40500-750 mm high -1.412.132.973.454.3012.01750-1000mm high -2.072.793.724.385.4312.62Cut Concrete Slabs Using Trolley Type Clipper Saw (m/hr)Ne 25 mm deep15.225-50 mm deep11.550-75 mm deep6.67 Cutting BackTask / DescriptionSlow Ave Fast Units Concrete Pile Caps, 50-300mm deep and 0.6m dia0.6 - 0.3 hrs/no Concrete Pile Caps, 300-750mm deep and 0.6m dia1.5 - 0.4 hrs/no Concrete Pile Caps, > 750mm deep and 0.6m dia1.8 - 0.8 hrs/no Concrete Pile Caps, 50-300mm deep and 1.1m dia1.9 - 0.8 hrs/no Concrete Pile Caps, 300-750mm deep and 1.1m dia2.5 - 1.1 hrs/no Concrete Pile Caps, > 750mm deep and 1.1m dia4.2 - 2.3 hrs/no Concrete Pile Caps, 50-300mm deep and 2.5m dia9.2 - 8.2 hrs/no Concrete Pile Caps, 300-750mm deep and 2.5m dia10.1 - 9.5 hrs/no Concrete Pile Caps, > 750mm deep and 2.5m dia11.5 - 10.2 hrs/no Concrete, Cutting Slabs, 5-25m deep- 15.2 - m/hr Concrete, Cutting Slabs, 25-50m deep- 11.5 - m/hr Concrete, Cutting Slabs, 50-75m deep- 6.7 - m/hr Concrete, Cutting Holes, coring machine- 0.2 - m3/hr Concrete, Cutting Back to expose couplers 0.7m slab- 2.5 - m/day | — | Cutting Back |
| Cutting ChasesDemolition & Break Out | Cutting ChasesTask / DescriptionSlow Ave Fast Units Concrete, cutting by hand, < 25mm wide1.5 2.1 3.1 m/hr Concrete, cutting by hand, 25-50mm wide1.2 1.6 2.5 m/hr Concrete, cutting by hand, 50-75mm wide1.0 1.4 2.1 m/hr Concrete, cutting by hand, 75-100mm wide0.9 1.2 1.8 m/hr Concrete, cutting by machine, < 25mm wide3.1 4.0 5.8 m/hr Concrete, cutting by machine, 25-50mm wide2.5 3.3 5.0 m/hr Concrete, cutting by machine, 50-75mm wide2.1 2.9 4.2 m/hr Concrete, cutting by machine, 75-100mm wide1.8 2.4 3.7 m/hr Brickwork, cutting by hand, < 25mm wide2.1 2.7 4.1 m/hr Brickwork, cutting by hand, 25-50mm wide1.6 2.3 3.5 m/hr Brickwork, cutting by hand, 50-75mm wide1.4 1.9 2.8 m/hr Brickwork, cutting by hand, 75-100mm wide1.2 1.6 2.5 m/hr Brickwork, cutting by machine, < 25mm wide4.2 5.5 11.1 m/hr Brickwork, cutting by machine, 25-50mm wide3.3 4.5 6.7 m/hr Brickwork, cutting by machine, 50-75mm wide3.3 4.5 6.7 m/hr Brickwork, cutting by machine, 75-100mm wide2.5 3.3 5.0 m/hr Light Blockwork, cutting by hand, < 25mm wide3.8 5.0 7.7 m/hr Light Blockwork, cutting by hand, 25-50mm wide3.2 4.2 6.3 m/hr Light Blockwork, cutting by hand, 50-75mm wide2.6 3.4 5.3 m/hr Light Blockwork, cutting by hand, 75-100mm wide2.3 3.1 4.5 m/hr Light Blockwork, cutting by machine, < 25mm wide7.7 10.0 14.2 m/hr Light Blockwork, cutting by machine, 25-50mm wide5.9 7.7 11.1 m/hr Light Blockwork, cutting by machine, 50-75mm wide5.2 7.2 10.0 m/hr Light Blockwork, cutting by machine, 75-100mm wide4.7 6.3 9.1 m/hr Heavy Blockwork, cutting by hand, < 25mm wide1.9 2.6 3.8 m/hr Heavy Blockwork, cutting by hand, 25-50mm wide1.6 2.1 3.2 m/hr Heavy Blockwork, cutting by hand, 50-75mm wide1.3 1.8 2.7 m/hr Heavy Blockwork, cutting by hand, 75-100mm wide1.2 1.5 2.3 m/hr Heavy Blockwork, cutting by machine, < 25mm wide3.8 5.0 7.7 m/hr Heavy Blockwork, cutting by machine, 25-50mm wide3.2 4.2 6.2 m/hr Heavy Blockwork, cutting by machine, 50-75mm wide2.7 3.6 5.2 m/hr Heavy Blockwork, cutting by machine, 75-100mm wide2.3 3.1 4.5 m/hr32 rate statements found; left for an editor | — | Cutting Chases |
| Cutting SwitchboxesDemolition & Break Out | Cutting SwitchboxesTask / DescriptionSlow Ave Fast Units Cutting in Concrete, small box7.1 9.5 12.5 no/hr Cutting in Concrete, large box3.6 4.5 5.6 no/hr Cutting in Brickwork, small box6.6 9.5 12.5 no/hr Cutting in Brickwork, large box4.2 5.3 6.3 no/hr Cutting in Lightweight Blockwork, small box20.0 23.0 25.0 no/hr Cutting in Lightweight Blockwork, large box10.0 12.5 14.3 no/hr Cutting in Heavyweight Blockwork, small box7.7 10.0 12.5 no/hr Cutting in Heavyweight Blockwork, large box3.8 4.8 5.9 no/hr8 rate statements found; left for an editor | — | Cutting Switchboxes |
| DeckingBuilding & Construction | DeckingTask / DescriptionSlow Ave Fast Units Simple Universal Beam Steel Bridge, concrete bridge deck, grano cover- 7.1 - m/day | — | Decking |
| Deep CompactionGround Compaction | Essentially required in order to reduce expected ground settlement and to protect underground utilities / structures etc.Deep compaction by 350 mm dia Vibroflot, 3 m centres in sand.Working on 12 hour basis, a vibroflot will achieve an output of 3-4,000 m3/shift (5,000 m3/day has been achieved in an extended shift).Ground CompactionTask / DescriptionSlow Ave Fast Units Deep Vibroflot, 3m centres330.0 380.0 465.0 m3/hr Vibro-Roller, Sand28.5 31.2 45.2 m2/hr Vibro-Roller, Soil- 58.8 - m2/hr Vibro-Roller, Clay- 55.6 - m2/hr Vibro-Roller, Hardcore- 38.4 - m2/hr Vibro-Roller, Ash- 57.8 - m2/hr4 rate statements found; left for an editor | — | Deep Compaction |
| Defence Sector | Defence Sector Production Rates & Build Times: | — | Defence Sector |
| Define First FixBuilding Services / E&M | Definition of Building Services - First Fix Environmental Control Systems This shall include the installation of all ECS equipment such as MCC's, fans and AHU's. In addition the installation of all primary and secondary ductwork and pipework systems (including valves, dampers, access panels, supports, anchors and guides) shall be completed. Where necessary, due to concealment or other construction restraints, sectional testing shall be completed. Electrical Systems This shall include the installation of all transformers and switchboards. In addition, the installation of all primary and secondary cable containment and support systems, such as ladder racks, cable trays, cable trucking and conduits including brackets, anchors and guides shall be completed. Plumbing, Drainage and Wet Fire Systems This shall include the installaion of all duty and standby pumps for flushing water system, sump pumps, potable water system, drencher system, water spray system, sprinkler system, fire services system, trackside fire fighting system. In addition, the installation of all primary and secondary pipe runs, whether horizontal or vertical, with associated valves, supports, anchors and guides. AFA System This shall include all primary and secondary cable containment for the AFA system. Where necessary, due to concealment or other construction restraints, sectional testing shall be completed. | — | Define First Fix |
| Define Second FixBuilding Services / E&M | Definition of Building Services - Second Fix Environmental Control Systems This shall include the installation of fan coils, EP panels and PLC panels. In addition, the insulation of all primary and secondary ductwork as well as pipework systems; leakage tests for ductwork and pipework; power and control cabling & wiring including termination; complete installation of pneumatic system. Electrical Systems This shall include the installation of isolators, sockets, lighting, distribution boards, UPS/CBS/Batteries. In addition, the installation and testing of all primary, secondary and final circuitry, cabling and wiring including terminations for isolators, sockets, lighting, transformers, switchboards, distribution boards, UPS/CBS/Batteries and any other power and control points shall be completed. All electrical installation and testing work must comply with the HV and LV Power On Dates. Plumbing and Drainage and Wet Fire Systems This shall include the installaion of the controls for flushing water system, sump pumps, potable water system, drencher system, water spray system, sprinkler system, fire services system, trackside fire fighting system. In addition, the power and control wiring and cabling including termination shall be completed. The hydraulic testing of all piping systems for pumps and the associated pipe works shall be completed. AFA Fire Systems This shall include cabling and wiring for AFA system, termination of cabling and wiring to the AFA panels and the AFA loops complete. This shall also include the installation of detector base plates. | — | Define Second Fix |
| DesignBridges | — | Design | |
| Design WorksTunnelling & Mining | — | Design Works | |
| DewateringDewatering | To setup a cofferdam dewatering system, including boring, pump installation and outflow pipework and drainage tanks etc, typical rates are...Small 2 hole system, for an overrun tunnel, with a single drilling rig takes about 7 - 10 days to get up and running.A larger system, with 10 - 15 holes, for a station type cofferdam will take in the region of 3 weeks with 2 rigs. This can be speeded up with the use of more rigs to reduce the well boring times.A typical rate of 2.5 days per pump installation can be used to calculate detailed pumping arrangements. The water level can be dropped in a "closed cofferdam" within a 6 to 8 hour period for a 25,000 m2 cofferdam with a 2 m water level reduction. For smaller closed areas it will take only a few hours at most to reduce the water level by 2.5 - 3 metres.Recharge System - Average well depth of say 55 m deep, not into rock, 9 wells in 10 days or 1.11 days/no with an additional 4 - 5 days to connect pipework and recharge backup tanks etc.DewateringTask / DescriptionSlow Ave Fast Units Setup small 2 hole system10.0 8.0 6.0 days Setup large 15 hole system- 21.0 - days Calculate system times per pump- 2.5 - days/pump Setup Recharge System- 3.5 - days/pump | — | Dewatering |
| Diaphragm WallingFoundation Works | — | Diaphragm Walling | |
| Doors & Window InstallationFacade Waterproofing | InstallationFor windows that are not 'built-in' as work proceeds...Install & Fix - By Area = 2.0 m2/hrInstall & Fix - By Girth = 4.0 m/hrMastic Pointing = 6.0 m/hrDoors and WindowsTask / DescriptionSlow Ave Fast Units Mastic Pointing to Frames- 9.5 - m/hr Fix Metal and Timber Windows After Wall Complete- 2.0 - m2/hr Window Glazing- 1.3 - m2/hr Window Glazing, Single Glazed Units- 2.0 - m2/hr Window Glazing, Double Glazed Units- 1.3 - m2/hr3 rate statements found; left for an editor | — | Doors & Window Installation |
| Drainage, Manholes and GulleysBuilding & Construction | Manholes and GulleysTask / DescriptionSlow Ave Fast Units Concrete Pre-Cast Manhole Units, 610 x 455 x 51 mm- 1.2 - hrs/no Concrete Pre-Cast Manhole Units, 990 x 610 x 64 mm- 1.6 - hrs/no Brickwork Manhole, 1.0 brick engineering- 0.3 - m2/hr Brickwork Manhole, 1.5 brick engineering- 0.2 - m2/hr Brickwork Manhole, 2.0 brick engineering- 0.2 - m2/hr Benching to Manhole, under 0.5m2- 0.9 - hrs/no Benching to Manhole, 0.5-0.75m2- 1.2 - hrs/no Benching to Manhole, 0.75-1.0m2- 1.8 - hrs/no Brickwork Manhole, build in pipes, under 150mm dia- 0.1 - hrs/no Brickwork Manhole, build in pipes, 150-225mm dia- 0.2 - hrs/no Brickwork Manhole, build in pipes, over 225mm dia- 0.3 - hrs/no Brickwork Manhole, build in cast iron covers0.3 0.6 1.2 hrs/no Yard Gulleys, 75-150mm dia pipes, bed and level- 2.2 - no/hr Yard Gulleys, 150-225mm dia pipes, bed and level- 1.8 - no/hr Yard Gulleys, 225-300mm dia pipes, bed and level- 1.5 - no/hr Road Gulleys, 600mm deep, bed and level- 1.2 - no/hr Road Gulleys, 750mm deep, bed and level- 0.8 - no/hr Road Gulleys, 900mm deep, bed and level- 0.4 - no/hr Road Gulleys, 1,200mm deep, bed and level- 0.3 - no/hr Road Gulleys, install gratings- 5.0 - no/hr PVC Manhole- 15.0 - mins/noLand DrainsTask / DescriptionSlow Ave Fast Units Land Drains, Concrete, butt jointed, under 150mm dia, 0-5m run- 11.6 - m/hr Land Drains, Concrete, butt jointed, under 150mm dia, 5-30m run- 14.1 - m/hr Land Drains, Concrete, butt jointed, under 150mm dia, over 30m run- 18.8 - m/hr Land Drains, Concrete, butt jointed, 150-225mm dia, 0-5m run- 8.4 - m/hr Land Drains, Concrete, butt jointed, 150-225mm dia, 5-30m run- 10.2 - m/hr Land Drains, Concrete, butt jointed, 150-225mm dia, over 30m run- 11.9 - m/hr Land Drains, Concrete, butt jointed, 225-300mm dia, 0-5m run- 5.4 - m/hr Land Drains, Concrete, butt jointed, 225-300mm dia, 5-30m run- 6.5 - m/hr Land Drains, Concrete, butt jointed, 225-300mm dia, over 30m run- 7.9 - m/hrDrainageTask / DescriptionSlow Ave Fast Units PVC Drainage, 1m pipes, 100-150mm dia, 0-5m run- 5.7 - m/hr PVC Drainage, 1m pipes, 100-150mm dia, 5-30m run- 8.1 - m/hr PVC Drainage, 1m pipes, 100-150mm dia, over 30m run- 9.5 - m/hr PVC Drainage, 3m pipes, 100-150mm dia, 0-5m run- 12.2 - m/hr PVC Drainage, 3m pipes, 100-150mm dia, 5-30m run- 15.2 - m/hr PVC Drainage, 3m pipes, 100-150mm dia, over 30m run- 18.2 - m/hr PVC Drainage, 6m pipes, 100-150mm dia, 0-5m run- 22.2 - m/hr PVC Drainage, 6m pipes, 100-150mm dia, 5-30m run- 27.7 - m/hr PVC Drainage, 6m pipes, 100-150mm dia, over 30m run- 33.3 - m/hr PVC Drainage, 3m pipes, 150-200mm dia, 5-30m run- 10.6 - m/hr PVC Drainage, 3m pipes, 150-200mm dia, over 30m run- 12.8 - m/hr PVC Drainage, 6m pipes, 150-200mm dia, 5-30m run- 21.2 - m/hr PVC Drainage, 6m pipes, 150-200mm dia, over 30m run- 25.6 - m/hr Stoneware Drainage, Cement/Sand Joints, 75mm dia, 0-5m run- 4.7 - m/hr Stoneware Drainage, Cement/Sand Joints, 75mm dia, 5-30m run- 5.5 - m/hr Stoneware Drainage, Cement/Sand Joints, 75mm dia, over 30m run- 6.6 - m/hr Stoneware Drainage, Cement/Sand Joints, 100mm dia, 0-5m run- 4.4 - m/hr Stoneware Drainage, Cement/Sand Joints, 100mm dia, 5-30m run- 5.0 - m/hr Stoneware Drainage, Cement/Sand Joints, 100mm dia, over 30m run- 6.2 - m/hr Stoneware Drainage, Cement/Sand Joints, 150mm dia, 0-5m run- 3.2 - m/hr Stoneware Drainage, Cement/Sand Joints, 150mm dia, 5-30m run- 3.8 - m/hr Stoneware Drainage, Cement/Sand Joints, 150mm dia, over 30m run- 4.5 - m/hr Stoneware Drainage, Cement/Sand Joints, 225mm dia, 0-5m run- 2.1 - m/hr Stoneware Drainage, Cement/Sand Joints, 225mm dia, 5-30m run- 2.6 - m/hr Stoneware Drainage, Cement/Sand Joints, 225mm dia, over 30m run- 3.1 - m/hr Stoneware Drainage, Cement/Sand Joints, 300mm dia, 0-5m run- 1.4 - m/hr Stoneware Drainage, Cement/Sand Joints, 300mm dia, 5-30m run- 1.7 - m/hr Stoneware Drainage, Cement/Sand Joints, 300mm dia, over 30m run- 2.4 - m/hr Stoneware Drainage, Cement/Sand Joints, over 375mm dia, 0-5m run- 1.1 - m/hr Stoneware Drainage, Cement/Sand Joints, over 375mm dia, 5-30m run- 1.3 - m/hr Stoneware Drainage, Cement/Sand Joints, over 375mm dia, over 30m run- 1.6 - m/hr Stoneware Drainage, Flexible Joints, 75mm dia, 0-5m run- 8.3 - m/hr Stoneware Drainage, Flexible Joints, 75mm dia, 5-30m run- 10.0 - m/hr Stoneware Drainage, Flexible Joints, 75mm dia, over 30m run- 12.5 - m/hr Stoneware Drainage, Flexible Joints, 100mm dia, 0-5m run- 7.7 - m/hr Stoneware Drainage, Flexible Joints, 100mm dia, 5-30m run- 9.1 - m/hr Stoneware Drainage, Flexible Joints, 100mm dia, over 30m run- 10.0 - m/hr Stoneware Drainage, Flexible Joints, 150mm dia, 0-5m run- 5.2 - m/hr Stoneware Drainage, Flexible Joints, 150mm dia, 5-30m run- 6.2 - m/hr Stoneware Drainage, Flexible Joints, 150mm dia, over 30m run- 7.7 - m/hr Stoneware Drainage, Flexible Joints, 225mm dia, 0-5m run- 2.7 - m/hr Stoneware Drainage, Flexible Joints, 225mm dia, 5-30m run- 3.3 - m/hr Stoneware Drainage, Flexible Joints, 225mm dia, over 30m run- 4.0 - m/hr Stoneware Drainage, Flexible Joints, 300mm dia, 0-5m run- 1.7 - m/hr Stoneware Drainage, Flexible Joints, 300mm dia, 5-30m run- 2.1 - m/hr Stoneware Drainage, Flexible Joints, 300mm dia, over 30m run- 2.5 - m/hr Stoneware Drainage, Flexible Joints, over 375mm dia, 0-5m run- 1.4 - m/hr Stoneware Drainage, Flexible Joints, over 375mm dia, 5-30m run- 1.6 - m/hr Stoneware Drainage, Flexible Joints, over 375mm dia, over 30m run- 2.1 - m/hr PVC, Stoneware, Pitch Fibre & Concrete Joints- 2.4 - mins/no Pitch Fibre Pipes, 75mm dia, 0-5m run- 9.1 - m/hr Pitch Fibre Pipes, 75mm dia, 5-30m run- 16.6 - m/hr Pitch Fibre Pipes, 75mm dia, over 30m run- 20.0 - m/hr Pitch Fibre Pipes, 100mm dia, 0-5m run- 9.1 - m/hr Pitch Fibre Pipes, 100mm dia, 5-30m run- 16.6 - m/hr Pitch Fibre Pipes, 100mm dia, over 30m run- 20.0 - m/hr Pitch Fibre Pipes, 150mm dia, 0-5m run- 6.6 - m/hr Pitch Fibre Pipes, 150mm dia, 5-30m run- 12.5 - m/hr Pitch Fibre Pipes, 150mm dia, over 30m run- 14.3 - m/hr Pitch Fibre Pipes, 200mm dia, 0-5m run- 6.2 - m/hr Pitch Fibre Pipes, 200mm dia, 5-30m run- 11.1 - m/hr Pitch Fibre Pipes, 200mm dia, over 30m run- 12.5 - m/hr Pitch Fibre Pipes, 225mm dia, 0-5m run- 5.8 - m/hr Pitch Fibre Pipes, 225mm dia, 5-30m run- 10.0 - m/hr Pitch Fibre Pipes, 225mm dia, over 30m run- 12.1 - m/hr Hepsleve Rubber Joint System, 75mm dia, 0-5m run- 12.5 - m/hr Hepsleve Rubber Joint System, 75mm dia, 5-30m run- 14.3 - m/hr Hepsleve Rubber Joint System, 75mm dia, over 30m run11.2 16.6 30.1 m/hr Hepsleve Rubber Joint System, 100mm dia, 0-5m run- 10.0 - m/hr Hepsleve Rubber Joint System, 100mm dia, 5-30m run- 12.5 - m/hr Hepsleve Rubber Joint System, 100mm dia, over 30m run- 14.3 - m/hr Hepsleve Rubber Joint System, 150mm dia, 0-5m run- 7.1 - m/hr Hepsleve Rubber Joint System, 150mm dia, 5-30m run- 9.1 - m/hr Hepsleve Rubber Joint System, 150mm dia, over 30m run8.3 10.0 13.8 m/hr Hepsleve Rubber Joint System, 225mm dia, 0-5m run- 6.8 - m/hr Hepsleve Rubber Joint System, 225mm dia, 5-30m run- 4.5 - m/hr Hepsleve Rubber Joint System, 225mm dia, over 30m run- 5.5 - m/hr Hepsleve Rubber Joint System, 300mm dia, 0-5m run- 2.5 - m/hr Hepsleve Rubber Joint System, 300mm dia, 5-30m run- 2.9 - m/hr Hepsleve Rubber Joint System, 300mm dia, over 30m run- 3.7 - m/hr Hepsleve Rubber Joint System, over 375mm dia, 0-5m run- 1.9 - m/hr Hepsleve Rubber Joint System, over 375mm dia, 5-30m run- 2.3 - m/hr Hepsleve Rubber Joint System, over 375mm dia, over 30m run- 2.7 - m/hr Concrete Pipes, 1.5m pipes, 375mm dia, 0-5m run- 2.8 - m/hr Concrete Pipes, 1.5m pipes, 375mm dia, 5-30m run- 3.4 - m/hr Concrete Pipes, 1.5m pipes, 375mm dia, over 30m run- 3.8 - m/hr Concrete Pipes, 1.5m pipes, 450mm dia, 0-5m run- 2.7 - m/hr Concrete Pipes, 1.5m pipes, 450mm dia, 5-30m run- 3.2 - m/hr Concrete Pipes, 1.5m pipes, 450mm dia, over 30m run- 3.6 - m/hr Concrete Pipes, 1.5m pipes, 525mm dia, 0-5m run- 2.5 - m/hr Concrete Pipes, 1.5m pipes, 525mm dia, 5-30m run- 2.9 - m/hr Concrete Pipes, 1.5m pipes, 525mm dia, over 30m run- 3.4 - m/hr Concrete Pipes, 1.5m pipes, 600mm dia, 0-5m run- 2.4 - m/hr Concrete Pipes, 1.5m pipes, 600mm dia, 5-30m run- 2.7 - m/hr Concrete Pipes, 1.5m pipes, 600mm dia, over 30m run- 3.3 - m/hr Concrete Pipes, 1.5m pipes, 675mm dia, 0-5m run- 2.2 - m/hr Concrete Pipes, 1.5m pipes, 675mm dia, 5-30m run- 2.6 - m/hr Concrete Pipes, 1.5m pipes, 675mm dia, over 30m run- 2.9 - m/hr Concrete Pipes, 1.5m pipes, 750mm dia, 0-5m run- 1.1 - m/hr Concrete Pipes, 1.5m pipes, 750mm dia, 5-30m run- 2.4 - m/hr Concrete Pipes, 1.5m pipes, 750mm dia, over 30m run- 2.5 - m/hr Concrete Pipes, 1.5m pipes, 1,050mm dia- 2.9 4.2 m/day Concrete Pipes, 1.5m pipes, 1,500mm dia- 2.5 3.8 m/day Concrete Pipes, 1.5m pipes, 1,800mm dia- 2.1 2.6 m/day Concrete Pipes, 2.5m pipes, 375mm dia, 0-5m run- 3.6 - m/hr Concrete Pipes, 2.5m pipes, 375mm dia, 5-30m run- 4.3 - m/hr Concrete Pipes, 2.5m pipes, 375mm dia, over 30m run- 5.0 8.0 m/hr Concrete Pipes, 2.5m pipes, 450mm dia, 0-5m run- 3.4 - m/hr Concrete Pipes, 2.5m pipes, 450mm dia, 5-30m run- 4.1 - m/hr Concrete Pipes, 2.5m pipes, 450mm dia, over 30m run- 4.5 9.0 m/hr Concrete Pipes, 2.5m pipes, 525mm dia, 0-5m run- 3.3 - m/hr Concrete Pipes, 2.5m pipes, 525mm dia, 5-30m run- 3.8 - m/hr Concrete Pipes, 2.5m pipes, 525mm dia, over 30m run- 4.1 - m/hr Concrete Pipes, 2.5m pipes, 600mm dia, 0-5m run- 3.0 - m/hr Concrete Pipes, 2.5m pipes, 600mm dia, 5-30m run- 3.5 - m/hr Concrete Pipes, 2.5m pipes, 600mm dia, over 30m run- 4.0 - m/hr Concrete Pipes, 2.5m pipes, 675mm dia, 0-5m run- 2.8 - m/hr Concrete Pipes, 2.5m pipes, 675mm dia, 5-30m run- 3.3 - m/hr Concrete Pipes, 2.5m pipes, 675mm dia, over 30m run- 3.7 - m/hr Concrete Pipes, 2.5m pipes, 750mm dia, 0-5m run- 2.6 - m/hr Concrete Pipes, 2.5m pipes, 750mm dia, 5-30m run- 3.1 - m/hr Concrete Pipes, 2.5m pipes, 750mm dia, over 30m run- 3.6 - m/hr Lay Shingle Around Pipework, under 150mm dia- 7.0 - m/hr Lay Shingle Around Pipework, over 150mm dia4.0 5.5 9.0 m/hr8 rate statements found; left for an editor | — | Drainage, Manholes and Gulleys |
| Drill & Blast MethodTunnelling & Mining | — | Drill & Blast Method | |
| Driven PilesFoundation Works | West Piling (P.C. Shells), Rate of 100 m/day Balken Piling (Solid P.C. Pile), Rate of 120 - 135 m/day H-Piling, Rate of 200 - 500 m/day3 rate statements found; left for an editor | — | Driven Piles |
| Electrical SystemRailways | Electrical SystemTask / DescriptionSlow Ave Fast Units Railway Station 1st Fix- 38.0 - wks Railway Station 2nd Fix- 16.0 - wks Railway Station T&C- 8.0 - wks Cable Installation, 1 cable laid in trench and protect- 6.2 - m/hr Cable Installation, 2 cable laid in trench and protect- 5.6 - m/hr Cable Installation, 5 cable laid in trench and protect- 4.3 - m/hr Cable Installation, 7 cable laid in trench and protect- 3.7 - m/hr Cable Installation, 8 cable laid in trench and protect- 3.5 - m/hr Cable Installation, 2 cable laid in trench and protect, 100mm dia- 1.8 - m/hr Cable Installation, 2 cable laid in trench and protect, 135mm dia- 1.6 - m/hr Cable Installation, 3 cable laid in trench and protect, 100mm dia- 1.0 1.5 m/hr Cable Installation, 6 cable laid in trench and protect, 100mm dia- 0.7 1.2 m/hr Cable Installation, 4 cable laid in trench and protect, 150mm dia0.7 1.2 3.1 m/hr Cable Installation, 36 cable laid in trench and protect, 100mm dia- 0.2 - m/hr Cable Installation, 10 cable laid in trench and protect, 100mm dia- 0.5 - m/hr Cable Installation, 1 cable laid in trench and protect, 300mm dia- 1.3 - m/hr3 rate statements found; left for an editor | — | Electrical System |
| Elevated WatercourseWater Management | Modification of an existing 6 m high elevated canal. Normal canal is 12 m in width, to allow single passing on bridge/aqueduct structures, a 5.5 m minimum width is required. Normal depth of water is 1.3 m. Some 4 number "V" shaped piers on 1,200 mm bored piles, each 20m deep, supported a central span of 40 m with 17 m elevated "run on" section between the piers and ground abutments. Overall length 75 m and 5.5 m wide water course and 3.5 m footways on each side. Clay dams were installed at each end, canal was drained (fish removed !) with some 35,000 m3 of excavation removed. Overall time period = 38 weeks Construct new lock = 29 weeks | — | Elevated Watercourse |
| Epoxy WaterproofingFacade Waterproofing | Epoxy based material (eliminator etc), a 2 part mix. It is sprayed on and large areas can be completed in a short time. Usually carried out in two coats, good ventilation is required. A one coat application = 75 m2/hr A two coat application = 38 m2/hr2 rate statements found; left for an editor | — | Epoxy Waterproofing |
| Equipment Conveying decksConveying Systems | Conveying decks may be used in a variety of industries, for example in airport baggage handling systems or cargo handling systems. | — | Equipment Conveying decks |
| Escalator Installation Building Services / E&M | Modular Design Escalators PackagesThe escalator trusses are usually delivered in 1.6 m cubes, which include the internal workings etc. Normally 3 to 4 sections go to make up a standard escalator (an 11 m rise), however sizes and lengths vary greatly.Delivery ImplicationsThe largest single element is the nose piece which is approximately 1.8 m wide, 3 m long and 2.5 m high. This section weight 1,500 kg. The other truss sections weight only 1,000 kg at most. The maximum weight of an entire escalator (10 m rise) is estimated at 15,000 kg. It is usual to being the escalators in from the top landing and lower the whole truss down into its final position. Power supply being 415 volt 3 phase hard wired, T&C may be done with temporary supplies.Typical Project StrategySequence /timing of works:16 wks = Develop concept design / submit for approval.12 wks = Prepare preliminary design / submit for approval.60 wks = Manufacture, test & site delivery, in conjunction with completion of final design.4 wks = Initial delivery placing and connection of truss sections.12-16 wks = Install escalators and commission.12 wks = Test running of escalators.12 wks = Trial running of escalators / System Operational.Typical Escalator Installation Sequence Timing of single escalator:1 wks = Assemble sections and truss position, align, level.6 wks = Escalator contractor "stop work" period, to allow ABWF contractor to complete surrounding finishes.5 wks = Final escalator installation, "Phase B" decking installation and glazing etc.0 wks = Escalator Power-On required.2 wks = Test performance "Phase C" prior to escalator Test Running.2 wks = Full load test "Phase D" of escalator.1 wks = Final test "Phase E"1 wks = EMSD Inspection of installation.1 wks = "Phase F" inspection.Total installation time being 12 - 14 weeks, excluding the "Stop Work" period during which the civil finishing works are completed.Task / DescriptionSlow Ave Fast Units Truss type, Overall Installation (excl arch finishes)14.0 12.0 11.0 wks Truss type, Manufacture, test and deliver- 60.0 48.0 wks Truss type, Phase A assemble truss , position/level- 1.0 - wks Truss type, Stop-Work for surrounding finishes8.0 6.0 4.0 wks Truss type, Phase B decking and glazing etc- 5.0 - wks Truss type, Phase C performance testing- 2.0 - wks Truss type, Phase D full load testing- 2.0 - wks Truss type, Phase E final test and inspection- 2.0 - wks | — | Escalator Installation |
| Excavate & LoadExcavation Works | Excavate Spoil Heaps and Load to Transport (m3/hr): Material0.6 m30.8 m31.0 m31.2 m3Sand/Soil20.025.630.335.7Gravel20.425.631.337.0Clay/Chalk18.523.227.833.3Boulder Clay16.921.324.430.3Note:0.6m3, 0.8m3, 1.0m3 and 1.2m3 are excavator bucket capacity.20.0, 25.6, 30.3 and 35.7 etc are excavation rates in m3 / hr | — | Excavate & Load |
| Excavate & Reduce LevelsEarthworks & Excavation | Excavate By Hand Trenches (m3/hr) Depth in Metres->Ne 1.51.5-3.03.0-4.5 Sand/Soil lose0.660.450.33Sand/Soil firm0.570.380.28Gravel0.450.310.23Clay/Heavy Soil0.460.310.24Boulder Clay0.380.260.19Pits or Bases Ne 2 m2 (m3/hr) Depth in Metres->Ne 1.51.5-3.03.0-4.5Sand/Soil lose0.50.33 -Sand/Soil firm0.430.29 -Gravel0.340.23 -Clay/Heavy Soil0.350.24 -Boulder Clay0.280.19 - Hand Transportation of Spoil (m3/hr) Wheel 0 - 10 m6.2510 - 20 m3.2320 - 50 m2.13 Trim Excavation (m3/hr) Ave ThicknessSandGravelClayBoulders0 - 25 mm20.0016.6720.0014.2925 - 50 mm11.11 8.33 9.097.6950 - 75 mm7.69 5.88 6.25 5.0075 - 125 mm 5.56 4.35 4.55 3.70Reduced Levels (D6 Dozer) Not Ex .25m - 45m3 per hrNot Ex 1m - 60m3 per hrEx 1m - 75m3 per hr3 rate statements found; left for an editor | — | Excavate & Reduce Levels |
| Excavate and RemoveBasement Excavations | Excavate and RemoveTask / DescriptionSlow Ave Fast Units Excavate Spoil Heaps to Transport, 0.6m3 bucket, Sand/Soil14.5 20.0 25.6 m3/hr Excavate Spoil Heaps to Transport, 0.6m3 bucket, Gravel Beds15.2 20.4 25.6 m3/hr Excavate Spoil Heaps to Transport, 0.6m3 bucket, Clay/Chalk12.3 18.5 23.2 m3/hr Excavate Spoil Heaps to Transport, 0.6m3 bucket, Boulder Clay11.2 16.9 21.3 m3/hr Excavate Spoil Heaps to Transport, 1.1m3 bucket, Sand/Soil25.4 30.3 35.7 m3/hr Excavate Spoil Heaps to Transport, 1.1m3 bucket, Gravel Beds25.6 31.3 37.0 m3/hr Excavate Spoil Heaps to Transport, 1.1m3 bucket, Clay/Chalk22.5 27.8 33.3 m3/hr Excavate Spoil Heaps to Transport, 1.1m3 bucket, Boulder Clay18.9 24.4 30.3 m3/hr Load Spoil to Barge, capacity 2,000m3- 8.0 - hrs Load Spoil to Barge, capacity 1,500m3- 6.5 - hrs Load Spoil to Barge, capacity 1,000m3- 5.5 - hrs Spoil conveyor, 600mm belt, 150m/min- 260.0 - m3/hr8 rate statements found; left for an editor | — | Excavate and Remove |
| ExternallySteel | One coat primer, 2 undercoats, 1 gloss 1.70 m2/hr As above to steel stanchions and beams 0.90 m2/hr As above to balustrades, railings etc 1.00 m2/hr As above to gutter and downpipes etc 2.50 m/hr4 rate statements found; left for an editor | — | Externally |
| Facade CleaningFacade Waterproofing | Water Jetting = 25.0 m2/day Acid Etching = 9.0 m2/day Grit Blasting = 12.0 m2/day3 rate statements found; left for an editor | — | Facade Cleaning |
| Felt RoofsFlat & Layered Roofs | Built-Up Felt Roofs Usually carried out with a minimum of a 1 man gang with a labourer. Large Roof Areas = 52 m2/day Smaller or Complicated Areas = 35 m2/day2 rate statements found; left for an editor | — | Felt Roofs |
| Fencing WorksBuilding & Construction | Fencing WorksTask / DescriptionSlow Ave Fast Units Site Hoarding, timber posts, plywood nailed to horizontal rails1.0 1.2 - m/hr Post Erection, Timber / Metal, dig, erect, fix3.3 4.5 - no/hr Post Erection, Concrete, dig, erect, fix3.2 4.0 - no/hr Fence Erection, Chainlink, posts at 1.5m- 4.2 - m/hr Fence Erection, Chainlink, posts at 2.0m- 4.4 - m/hr Fence Erection, Chainlink, posts at 3.0m- 5.5 - m/hr Fence Erection, Chestnut Pailings, posts at 1.5m- 23.8 - m/hr Fence Erection, Chestnut Pailings, posts at 2.0m- 33.3 - m/hr Fence Erection, Chestnut Pailings, posts at 3.0m- 41.6 - m/hr Fence Erection, Barbed Wire, posts at 1.5m- 71.4 - m/hr Fence Erection, Barbed Wire, posts at 2.0m- 100.0 - m/hr Fence Erection, Barbed Wire, posts at 3.0m- 125.0 - m/hr Gate Erection, Chainlink on frame- 4.1 - no/hr | — | Fencing Works |
| Fibre CablesBuilding Services / E&M | There are 4 phases to laying fibre cables - The laying of the duct, the pulling of the fibre cable, the splicing/terminating of the cable and the testing of the cable.The production rate for the laying of the duct will be as any similar small diameter pipe and dependent on the location and linear distance.The cable pulling phase has less to do with the length of the pull and much more to do with the number of pulls required - ie draw pit to draw pit distance is less important than the number of times the cable pulling operation is started and stopped. Production is therefore the number of pulls per day. The installers will generally attempt to install the cable from termination point to termination point in one day. Depending on the environment, an assumption of one pull a day is conservative and 2 a day being more optimistic. Crew sizes are small, 3/4 operatives.The termination is obviously a speciallist job and likely to be carried out by different small crew than the pulling of the cable.The duration is dependent on the number of fibres in the cable, but an assumption of one day per location and another day for testing at that location is reasonable. | — | Fibre Cables |
| Final FinishesBridges | — | Final Finishes | |
| Floating Track SlabRailways | Pre-cast concrete blocks that support standard steel tracks. They are used to reduce noise and vibration as the pre-cast track slab blocks are placed on resin pads (4 no per unit), held in place by fixed side and end restraint blocks. Side restraints, 0.8 m long, 12 no/day = 9.6 m/day Resin pads, 10 no/day = 10.0 m/day FST Units, 5 no/day = 10.0 m/day The above rates were achieved with a 6 man team, but could have been be speeded up by 200 300 % if a works train was available to hoist the units into place. The above was done with a "A" frame and chain hoist.6 rate statements found; left for an editor | — | Floating Track Slab |
| Floor FinishesFitout & Finishes | Floor FinishesTask / DescriptionSlow Ave Fast Units Granolithic Flooring- 3.1 - m2/hr Terrazzo Flooring, in-situ- 3.6 - m2/hr Terrazzo Flooring, pre-cast- 4.6 5.1 m2/hr Mosaic Tiling, 0.045x0.045m- 1.5 2.2 m2/hr Clay, quarry Tiles, small areas, much cutting- 0.8 1.1 m2/hr Clay, quarry Tiles, large areas, little cutting- 2.2 2.8 m2/hr Raised Floor System- 2.6 - m2/hr Linolium/Thermo-Plastic Flooring- 3.1 5.0 m2/hr Thermo-Plastic Floor Tiles- 3.3 5.6 m2/hr Wood Block Flooring, lay blocks- 1.5 2.1 m2/hr Wood Block Flooring, sand and polish- 3.1 - m2/hr Carpeting, Underlay & Gripper- 5.6 6.1 m2/hr Carpeting, Adhesive Fixing- 3.5 4.2 m2/hr Carpeting, Fully Fitted- 2.0 2.8 m2/hr Hardboard Sheeting Coverings, small areas- 3.7 4.1 m2/hr Hardboard Sheeting Coverings, large areas- 6.6 7.2 m2/hr Floor Sheeting Coverings, Lay Lino- 9.5 10.5 m2/hr13 rate statements found; left for an editor | — | Floor Finishes |
| FloorsPainting & Decorations | Epoxy floor paint 2.95 m2/hr | 2.95 m2 per hrper hrParsed | Floors |
| Footing formworkFormwork | ActivityTASKSTask - UOMLabor (L) - Carpenter (Mandays)Labor (L) - Helper (Mandays)Material (M)Material (M)Material (M)Footing formworkFooting - Shuttering & Providing SupportSqm0.8 Mandays/10Sqm1.5 Mandays/10SqmMS Wall Form Panel - 1250 x 500 : 16Nos/10SqmProps - 2m to 3m Long : 2 Nos/RmShuttering Oil : 4Ltr/10Sqm Footing - Deshuttering & insitu StackingSqm0.48 Mandays/10Sqm0.9 Mandays/10Sqm | — | Footing formwork |
| Footing ReinforcementReinforcement | ActivityTASKSTask - UOML - Barbender/Fitter (Mandays)L - Helper (Mandays)MMMFooting ReinforcementFoot Rein - Placing in Position & Binding - Using TMT Bars, Mild Steel, Tor SteelMt0.28 Mandays/0.1Mt0.38 Mandays/0.1MtBars - Include 5% WastageBinding Wire : 5 kg/0.1MtCover Blocks - 10No/0.1Mt Foot Rein - Straightening, Cutting (With Machine Cutting), bending - Using TMT Bars, Mild Steel, Tor SteelMt0.2 Mandays/0.1Mt0.28 Mandays/0.1MtBars - Include 5% Wastage Foot Rein - Straightening, Cutting (With Manual Cutting), bending - Using TMT Bars, Mild Steel, Tor SteelMt0.29 Mandays/0.1Mt0.32 Mandays/0.1MtBars - Include 5% Wastage | — | Footing Reinforcement |
| FormworkFormwork | FormworkTask / DescriptionSlow Ave Fast Units Pilecaps, < 0.7m20.9 1.6 2.0 m2/hr Pilecaps, 0.7-2.5m21.6 2.0 2.3 m2/hr Pilecaps, 2.5-3.0m22.0 2.3 2.5 m2/hr Pilecaps, > 3.0m22.3 2.5 3.1 m2/hr Ground Beams, < 0.7m21.1 1.7 1.8 m2/hr Ground Beams, 0.7-1.5m21.7 1.8 2.5 m2/hr Ground Beams, 1.5-3.0m21.8 2.5 2.6 m2/hr Ground Beams, 3.0-5.0m22.5 2.6 3.5 m2/hr Elevated Plain Slab Soffit0.6 0.8 1.2 m2/hr Beams, on erected falsework, width 100-200mm0.9 1.0 1.1 m2/hr Beams, on erected falsework, width 200-300mm1.0 1.1 1.3 m2/hr Beams, on erected falsework, width 300-500mm1.2 1.3 1.5 m2/hr Beams, on erected falsework, width 500-750mm1.5 1.6 1.8 m2/hr Beams, on erected falsework, width over 750mm1.4 1.5 1.7 m2/hr Walls, Construct Kickers5.3 7.1 10.0 m2/hr Walls, Fully Framed Formwork/Struts, 1.0-2.0m20.9 1.8 1.9 m2/hr Walls, Fully Framed Formwork/Struts, 2.0-5.0m21.0 2.2 2.5 m2/hr Walls, Fully Framed Formwork/Struts, over 5.0m21.2 2.5 2.9 m2/hr Walls, StoriForm Shutters, 1.0-3.0m21.0 1.4 2.0 m2/hr Walls, StoriForm Shutters, 3.0-5.0m21.9 2.3 3.3 m2/hr Walls, StoriForm Shutters, 5.0-10.0m22.3 2.8 3.5 m2/hr Walls, StoriForm Shutters, 10.0-15.0m23.2 4.5 4.0 m2/hr Walls, StoriForm Shutters, over 15.0m23.8 4.8 5.4 m2/hr Ground Slabs1.0 1.5 1.8 m2/hr Columns, Construct Kickers, direct to slab3.2 4.1 5.4 no/hr Columns, Construct Kickers, suspended from soffit slab1.2 2.8 3.2 no/hr Columns, Square Sides, Timber Clamp/Prop, csa < 0.1m21.3 1.6 1.8 m2/hr Columns, Square Sides, Timber Clamp/Prop, csa 0.1-0.4m21.8 2.1 2.4 m2/hr Columns, Square Sides, Timber Clamp/Prop, csa over 0.4m22.0 2.3 2.5 m2/hr Columns, Square Sides, Steel Forms, 1.5 x 1.5 x 9.0m high7.9 9.5 10.3 m2/hr Columns, Square Sides, Steel Forms, 2.0 x 2.0 x 9.0m high6.9 7.5 8.3 m2/hr Columns, Square Sides, Steel Forms, 2.0 x 4.0 x 9.0m high8.5 10.2 12.0 m2/hr Columns, Round Sides, Sacrificial Plastic Mould, 3.0-4.0m dia3.5 4.5 6.0 m2/hr Columns, Round Sides, Steel Mould, 3.0-4.0m dia5.2 6.5 7.5 m2/hr Columns, Sloping Column Heads, extra over rate- 2.5 3.5 hrs/no Staircases, Stair Soffit, Sloping0.7 0.8 1.0 m2/hr Staircases, Stair Soffit, Flat Landing0.8 0.9 1.2 m2/hr Staircases, Wall Strings0.4 0.6 - m2/hr Staircases, Open Strings0.7 0.8 - m2/hr Staircases, Riser Boards fixed to strings- 2.5 2.8 m2/hr Staircases, Risers fixed to Strings- 2.3 2.6 m2/hr Waffle Flooring, 2.4m grid1.1 1.4 1.8 m2/hr Shaft Slip Forming- 300.0 500.0 mm/hr Table Form, Aluminum System, 400m2 bays2.1 3.2 3.8 m2/hr Table Form, H-Frame Steel Falsework, 400m2 bays1.9 3.0 3.5 m2/hr Tunnel Forms, Wall and Slab poured as one- 15.6 17.5 m2/hr Hollorib Decking, lay deck- 43.5 47.5 m2/hr Hollorib Decking, shear connecting studs- 29.3 31.2 m2/hr Stop Ends, no perforations2.8 3.5 4.2 m2/hr Stop Ends, minor perforations1.2 1.5 1.9 m2/hr Stop Ends, dense perforations0.9 1.1 1.4 m2/hr Box Outs, 0.01-0.05m27.6 8.2 9.1 no/hr Box Outs, over 0.05m23.1 3.9 4.5 no/hr Dummy Frames, under 3.0m24.5 6.2 7.1 no/hr Dummy Frames, over 3.0m23.1 3.7 4.5 no/hr52 rate statements found; left for an editor | — | Formwork |
| Formwork & BasesBridges | — | Formwork & Bases | |
| Formwork Re-UseFormwork | Typical rate for number of formwork uses before shutter remake. NOTE: This varies significantly depending on care taken with shutters and programme time available etc. Walls = 20 uses Slab Soffits = 10 - 15 uses Beam & Column Boxes = 30 uses | — | Formwork Re-Use |
| Glazing Facade Waterproofing | Glazing to windows, a typical rate of 1.23 m2/hr Sealed Glazing Units Single glazed units = 80.0 m2/wk Double glazed units = 45.0 m2/wk | 1.23 m2 per hrper hrParsed | Glazing |
| Granolithic Flooring Building & Construction | Typically carried out with a gang of 2 layers and a single labourer. Typical rate of 3.15 m2/hr | 3.15 m2 per hrper hrParsed | Granolithic Flooring |
| Gravel ChippingsThermal & Moisture Protection | Roof Protections Gravel & Chippings - Allow a rate of 1.4 tonnes/day for transporting and laying out solar reflective chippings. | 1.4 t per dayper dayParsed | Gravel Chippings |
| Ground ExcavationExcavation Works | Ground Excavation Rates (m3/hr):Ground TypeBucketBulk WorksBasementsTrenchesSmall & DeepSand/Soil0.3m38.78.07.18.4> 0.4m328.515.425.010.0 0.5m350.020.028.613.3Gravel0.3m37.16.96.14.5 0.4m325.914.322.28.7 0.5m340.018.128.611.1Clay/Chalk0.3m37.16.56.14.1 0.4m325.013.322.28.3 0.5m340.016.728.610.5V.Difficult0.3m36.15.95.44.1 0.4m322.211.820.07.7 0.5m328.611.820.06.7Small or Deep ExcavationsTask / DescriptionSlow Ave Fast Units Hydraulic Excavator, 0.3m3 bucket, Sand/Soil6.7 8.4 9.9 m3/hr Hydraulic Excavator, 0.3m3 bucket, Gravel Beds3.2 4.5 5.0 m3/hr Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk3.3 4.1 5.2 m3/hr Hydraulic Excavator, 0.3m3 bucket, Hard Ground3.3 4.1 5.2 m3/hr Hydraulic Excavator, 0.4m3 bucket, Sand/Soil8.2 10.0 11.7 m3/hr Hydraulic Excavator, 0.4m3 bucket, Gravel Beds7.1 8.7 10.2 m3/hr Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk6.5 8.3 9.4 m3/hr Hydraulic Excavator, 0.4m3 bucket, Hard Ground6.3 7.7 9.1 m3/hr Hydraulic Excavator, 0.5m3 bucket, Sand/Soil12.2 13.3 15.4 m3/hr Hydraulic Excavator, 0.5m3 bucket, Gravel Beds10.2 11.1 12.9 m3/hr Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk9.7 10.5 12.1 m3/hr Hydraulic Excavator, 0.5m3 bucket, Hard Ground6.1 6.7 7.7 m3/hr12 rate statements found; left for an editor | — | Ground Excavation |
| Ground MonitoringEarthworks & Excavation | — | Ground Monitoring | |
| GroutingGrouting Operations | Vertical Grout Curtain Application of grout curtain. A typical rate of 6.20 hrs/m run. | — | Grouting |
| Guttering & PipesRainwater Works | DownPipes 75 mm UPVC Pipes 3.3 m/hr 75 mm Cast Iron Pipes 2.1 m/hr 72 mm Aluminium Pipe System 2.5 m/hr Guttering 75 mm UPVC Gutter 3.1 m/hr 75 mm Cast Iron Gutter 2.5 m/hr 72 mm Aluminium Gutter System 2.9 m/hr Fittings A composite rate has been calculated to be used as an extra-over basis for all pipe fittings etc. 75 mm UPVC Fittings 3.1 no/hr 75 mm Cast Iron Fittings 2.2 no/hr 72 mm Aluminium Fittings 1.9 no/hr9 rate statements found; left for an editor | — | Guttering & Pipes |
| Hand Dug CaissonsFoundation Works | Principles Of Construction This type of "pile wall" is typical employed in areas where headroom or proximity to buildings restricts the use of large diameter bored pile drilling rigs, or where the wall is to be located very close to an existing structure. These are very time consuming and in allot of areas no-longer allowed as an acceptable safe construction method. Stringent air monitoring and safety isses are adhered to during the construction of the caisson. An electric chain block and hoist structure is maintained at the pile head for access and egress of both materials and operatives. Site Investigation / Advanced works Advanced grouting is often carried out around the group of caissons in order to reduce water inflow into the caisson area and provide adequate safety factor against base heave failer. Grouting of the area will also restrict ground settlement due to changes in the water table during caisson construction. A 75 mm diameter grout hole is drilled to 2 m belowthe specified toe of the caisson. On completion of drilling, a 40 mm inside diameter PVC, Tube-a-Manchette (T-A-M) grout tube will be installed to the bottom of the grout hole. The tube is usually perforated at 300 mm intervals with each perforation being covered by a tightly fitting rubber sleeve to act as one way valves. The grout hole is often backfilled with gravel and then pumped with grout to the specified pressures etc.. After each stage of grouting the T-A-M will be flushed with water to allow future grouting as necessary. The slightly conical excavation core is carried out by hand and a formwork erected and concrete placed in the void between the excavation and the internal formwork. Excavation down to the next level then begins. Excavation Of Caissons All excavation is carried out with air tools and shovels etc. Material is loaded into a 0.2 m3 drum skip. Hand excavation to a depth not exceeding 1 metre. Fix a suitably braced 3 segmented tapered shutter, fix reinformcement and pour concrete to fill all voids between the external face of the lining and the earth face. This operation is undertaken continously until the founding level is reached. Steel Reinforcement Reinformcement is placed either in prefabricated cages or directly erected in side the bores, depending on headroom and caisson access conditions. In some instances a steel "H" beam is installed in place of a reinforcement cage. Concreting Concrete is cast in place in one continuous operation using the tremmie pipe method, up to cutt-off level. The concrete is generally not vibrated. As-Built Examples Perimeter wall caissons, 800 mm diameter, excavated to a depth of 26 metres (HK Central Subway). Excavation Time 18 - 24 days Excavation to Concreteing Time 26 - 35 days Difficult ground of sea wall or ground obstructions can easily increase theoverall construction time to 50 or 150 days. | — | Hand Dug Caissons |
| Hand Fill & CompactGround Compaction | Loose from side of excavation, including compaction (m3/hr)... Material Ne 100m 100-200mm 200-300mm exc 300m Loose Sand/Soil 0.85 1.02 1.28 1.69 Clay/Heavy Chalk 0.77 0.92 1.16 1.56 Hoging 0.81 0.97 1.20 1.61 Hardcode 0.71 0.84 1.06 1.41 | — | Hand Fill & Compact |
| Health & Healthcare | Health & Healthcare Production Rates & Build Times: | — | Health & Healthcare |
| Hollorib DeckingFormwork | Hollorib Decking Lay decking = 350 m2/day Shear Connecting Studs 235 m2 studded per day per gun (4,000 studs/week) Concrete topping = 4,000 m2/week or 2,000 m2/week incl power floating3 rate statements found; left for an editor | — | Hollorib Decking |
| Housing DemolitionsDemolition & Break Out | DemolitionTask / DescriptionSlow Ave Fast Units Weight, Structural Steel- 2.5 - Tonnes/m3 Remove & Cart away, Ceramic Wall Tiles2.0 2.5 3.4 m2/hr Remove & Cart away, Wallpaper, 1 layer- 8.7 - m2/hr Remove & Cart away, Wallpaper, 2 layers- 7.1 - m2/hr Remove & Cart away, Wallpaper, 3 layers- 5.7 - m2/hr Remove & Cart away, Lathe and Plaster Ceilings3.2 4.6 5.0 m2/hr Remove & Cart away, Plaster to Walls2.1 3.1 5.9 m2/hr Remove & Cart away, External Render- 3.9 - m2/hr Remove & Cart away, Floor Screed- 3.2 - m2/hr Remove & Cart away, Concrete Paving- 4.0 - m2/hr Remove & Cart away, Brickwork Walls, 1.0 brick thick- 1.3 - m2/hr Remove & Cart away, Brickwork Walls, 0.5 brick thick- 2.6 - m2/hr Remove & Cart away, Brickwork Walls, Sand/Lime Mortar- 1.8 - hrs/100 Remove & Cart away, Fireplace and Hearth- 1.9 - hrs/no Remove & Cart away, Floor Boards- 6.2 - m2/hr Remove & Cart away, Skirting, Architrave, Dado rail etc- 16.5 - m/hr Remove & Cart away, Staircase- 7.3 - hrs/no Remove & Cart away, Windows, 0-1m2- 0.6 - hrs/no Remove & Cart away, Windows 1-2m2- 0.8 - hrs/no Remove & Cart away, Windows 2-3m2- 0.9 - hrs/no Remove & Cart away, Doors- 0.3 - hrs/on Remove & Cart away, Door Frame- 0.1 - hrs/no Remove & Cart away, Floor and Ceiling Joists- 1.1 - hrs/m Remove & Cart away, Wall Plates- 3.9 - hrs/m Remove & Cart away, Iron Bath- 1.4 - /hrs/no Remove & Cart away, Wash Basin/Sink- 0.8 - /hrs/no Remove & Cart away, Pipework including brackets etc- 6.1 - m/hr3 rate statements found; left for an editor | — | Housing Demolitions |
51–100 of 202
These values were contributed by members and reflect the conditions, methods and regions they worked in. They are a starting point for estimating, not a standard. Check them against your own records, the site conditions and the contract before relying on them.