Carpentry Carcassing
In the Open Standard
Started by admin ·
- Last updated
- Updated
- Views
- 7 views
This page is part of the Rates, Norms & Durations library.
Open the norms tables →Carpentry Carcassing
| Task / Description | Slow | Ave | Fast | Units |
| Windows, Timber Frames for Bricklaying | 1.1 | 0.5 | 0.1 | hrs/no |
| Windows, Drill, Screw & Plug extra over | 0.3 | 0.1 | - | hrs/no |
| Door Frames, Softwood, 1.0-3.0m2 | - | 0.2 | - | hrs/no |
| Door Frames, Softwood, 3.0-7.0m2 | 0.5 | 0.4 | - | hrs/no |
| Door Frames, Softwood, 7.0-10.0m2 | 1.2 | 0.8 | - | hrs/no |
| Door Frames, Hardwood, 1.0-3.0m2 | - | 0.3 | - | hrs/no |
| Door Frames, Hardwood, 3.0-7.0m2 | 0.6 | 0.3 | - | hrs/no |
| Door Frames, Hardwood, 7.0-10.0m2 | 1.4 | 1.0 | - | hrs/no |
| Erect Water Tank Platform | - | 2.3 | - | no/hr |
| Fix Studding For Bath | - | 0.1 | - | hrs/m |
| Cut Access Hatch | - | 0.3 | - | no/hr |
| Floor Joists, under 3m | 9.0 | 9.6 | 11.6 | no/hr |
| Floor Joists, 3.0-4.5m | 6.8 | 7.2 | 9.7 | no/hr |
| Floor Joists, 4.5-6.0m | 5.5 | 5.8 | 7.3 | no/hr |
| Ceiling Joists, under 3m | 12.8 | 14.0 | 14.7 | no/hr |
| Ceiling Joists, 3.0-4.5m | 10.8 | 12.1 | 12.6 | no/hr |
| Ceiling Joists, 4.5-6.0m | 9.6 | 10.8 | 11.1 | no/hr |
| Ceiling Joists, Notch to Beams | 20.0 | 25.0 | 28.5 | no/hr |
| Ceiling Joists, Pack Joist Ends | 20.1 | 23.8 | 26.3 | no/hr |
| Ceiling Joists, Nailing Joists together | - | 23.0 | - | m/hr |
| Ceiling Joists, Bolting Joists Together | - | 12.6 | - | m/hr |
| Floor Boards, Butt Jointed | - | 1.7 | - | m2/hr |
| Floor Boards, T&G Boards, under 75mm wide | - | 3.4 | - | m2/hr |
| Floor Boards, T&G Boards, 75-100mm wide | - | 3.8 | - | m2/hr |
| Floor Boards, T&G Boards, 100-125mm wide | - | 4.2 | - | m2/hr |
| Floor Boards, T&G Boards, 125-150mm wide | - | 5.5 | - | m2/hr |
| Plywood Sheeting, Butt Jointed, nailed | - | 9.1 | 10.2 | m2/hr |
| Plywood Sheeting, Butt Jointed, screwed | - | 4.1 | 4.8 | m2/hr |
| Plywood Sheeting, T&G Jointed, nailed | - | 8.3 | 9.1 | m2/hr |
| Plywood Sheeting, T&G Jointed, screwed | - | 4.0 | 4.6 | m2/hr |
| Chipboard Sheeting, Butt Jointed, nailed | - | 10.0 | 11.5 | m2/hr |
| Chipboard Sheeting, Butt Jointed, screwed | - | 5.1 | 5.8 | m2/hr |
| Chipboard Sheeting, T&G Jointed, nailed | - | 9.3 | 9.1 | m2/hr |
| Chipboard Sheeting, T&G Jointed, screwed | - | 5.5 | 5.9 | m2/hr |