Open the norms tables →Simple universal beam steel bridge in modular sections, welded on site. 16 truss sections each 15 m in length, supported on H-frame vertical columns / supports.
- Support Steelwork Fabrication (4 bays) = 25 days
- Support Steelwork Erection (4 bays) = 30 days
- Truss erections (4 bays) = 18 days
- Paintwork To Steel (16 bays) = 35 days
- Bridge Deck Concrete Works (16 bays) = 60 days (staggered)
- Bridge Lighting, Roof etc (16 bays) = 40 days
- Bridge Finishing, Handrails and Grano = 14 days
Structural Steelwork...
| Task / Description | Slow | Ave | Fast | Units |
| Simple Universal Beam Steel Bridge, erect support steel H frames | - | 1.2 | - | days/no |
| Simple Universal Beam Steel Bridge, erect 15m truss | - | 3.3 | - | m/day |