Rates, Norms & Durations
Carpentry Final Fixing
In the Open Standard
Started by admin ·
- Last updated
- Updated
- Views
- 9 views
This page is part of the Rates, Norms & Durations library.
Open the norms tables →Carpentry Final Fixing
| Task / Description | Slow | Ave | Fast | Units |
| Windows, Softwood, 3.0-7.0m2 | 0.6 | 0.4 | 0.3 | hrs/no |
| Windows, Softwood, 7.0-10.0m2 | 1.3 | 0.9 | 0.6 | hrs/no |
| Windows, Hardwood, 1.0-3.0m2 | 0.4 | 0.3 | - | hrs/no |
| Windows, Hardwood, 3.0-7.0m2 | 0.7 | 0.5 | 0.4 | hrs/no |
| Windows, Hardwood, 7.0-10.0m2 | 1.6 | 1.2 | 0.7 | hrs/no |
| Windows, Aluminum, 1.0-3.0m2 | 0.2 | 0.3 | - | hrs/no |
| Windows, Aluminum, 3.0-7.0m2 | 0.5 | 0.4 | 0.3 | hrs/no |
| Windows, Aluminum, 7.0-10.0m2 | 1.2 | 0.8 | 0.5 | hrs/no |
| Windows, Steel, 1.0-3.0m2 | 0.4 | 0.3 | 0.2 | hrs/no |
| Windows, Steel, 3.0-7.0m2 | 1.2 | 0.6 | 0.5 | hrs/no |
| Windows, Steel, 7.0-10.0m2 | 1.4 | 1.2 | 1.0 | hrs/no |
| Window Boards, nailed | - | 0.3 | 0.2 | hrs/m |
| Window Boards, screwed | - | 0.4 | 0.3 | hrs/m |
| Mouldings, Softwood, Nailed | - | 6.3 | 8.5 | m/hr |
| Mouldings, Softwood, Screwed | - | 4.6 | 5.6 | m/hr |
| Mouldings, Softwood, Gun Nailed | - | 8.2 | 11.1 | m/hr |
| Mouldings, Hardwood, Nailed | - | 3.3 | 5.5 | m/hr |
| Mouldings, Hardwood, Screwed | - | 2.4 | 3.7 | m/hr |
| Mouldings, Hardwood, Gun Nailed | - | 8.5 | 11.3 | m/hr |
| Skirting, Aluminum, Screwed 150-300mm centres | - | 7.6 | - | m/hr |
| Skirting, Aluminum, Screwed 300-450mm centres | - | 4.5 | - | m/hr |
| Skirting, Plastic, Adhesive Fixing | - | 8.6 | - | m/hr |
| Architrave Mouldings | 9.5 | 12.2 | 18.2 | m/hr |
| Architrave, Fix to Doors | - | 1.2 | - | hrs/door |
| Door Stop Mouldings | 10.1 | 16.9 | 25.0 | m/hr |
| Glazed Bead Mouldings | 15.5 | 18.6 | 20.4 | m/hr |
| Hanging Doors, Softwood, Single Pair Butts | 1.3 | 0.9 | 0.6 | hrs/no |
| Hanging Doors, Hardwood, Single Pair Butts | 1.9 | 1.2 | 0.9 | hrs/no |
| Cut Mortice to Receive Lock, Softwood | - | 0.2 | - | hrs/no |
| Cut Mortice to Receive Lock, Hardwood | - | 0.6 | - | hrs/no |
| Cut & Fix Formica Bath Panel | - | 0.4 | - | hrs/no |
| Kitchen Cupboards, Floor Units | - | 0.8 | 0.6 | hrs/no |
| Kitchen Cupboards, Wall Units | - | 0.7 | 0.5 | hrs/no |
| Kitchen Cupboards, Shelf Units | - | 0.8 | 0.7 | hrs/no |
| Staircase, pre-made, simple, straight flight | 1.9 | 1.5 | 1.1 | hrs/no |
| Staircase, pre-made, 2 straight flights, 1 landing | 3.7 | 2.9 | 2.6 | hrs/no |
| Staircase, pre-made, 2 straight flights, 2 landings | - | 6.3 | - | hrs/no |
| Staircase, Balustrades/Handrails, fix horizontal | 1.2 | 0.6 | 0.1 | hrs/no |
| Staircase, Balustrades/Handrails, fix raking | 0.9 | 0.5 | 0.3 | hrs/no |
| Staircase, Cut and Fix Newel to Walls | 0.9 | - | 0.2 | hrs/no |
| Windows, Softwood, 1.0-3.0m2 | 0.3 | 0.2 | - | hrs/no |
| Raised Flooring, metal system | - | 0.5 | - | m2/hr |