Rates, Norms & Durations
Common Brickwork
In the Open Standard
Started by admin ·
- Last updated
- Updated
- Views
- 9 views
This page is part of the Rates, Norms & Durations library.
Open the norms tables →Common Brickwork, by Machine (no/hr)
|
Hole depth (mm) -->
|
0-75
|
75-125
|
125-250
|
250-375
|
375-500
|
|
Ne 100 cm2
|
-
|
16.6
|
7.69
|
5.26
|
4.00
|
|
100-250 cm2
|
-
|
12.5
|
5.88
|
4.00
|
2.94
|
|
250-500 cm2
|
-
|
10.0
|
5.00
|
3.33
|
2.50
|
|
500-100 cm2
|
-
|
8.33
|
4.17
|
2.78
|
2.08
|
Common Brickwork, by Hand (no/hr)
|
Hole depth (mm) -->
|
0-75
|
75-125
|
125-250
|
250-375
|
375-500
|
|
Ne 100 cm2
|
11.1
|
8.33
|
5.56
|
3.85
|
-
|
|
100-250 cm2
|
9.09
|
7.14
|
4.55
|
3.23
|
-
|
|
250-500 cm2
|
7.69
|
5.88
|
3.85
|
2.70
|
-
|
|
500-100 cm2
|
6.67
|
4.76
|
3.23
|
2.27
|
-
|