Beam Falsework Formwork

Started by admin ·
Last updated
Updated
Views
8 views

This page is part of the Rates, Norms & Durations library.

Open the norms tables →

Rates include for making, fixing, cleaning and minor repair works etc, rates in m2/hr.

Soffits - On runners and props, including erection of props etc.

 

Hight of Beam Soffit--->  
   0 - 3.5 m
3.5 - 5.0 m
Width
Fix
Strike
Fix
Strike
 
 
 
 
 
100 - 200 mm
0.70
1.23
0.58
1.02
200 - 300 mm
0.81
1.39
0.68
1.15
300 - 500 mm
0.93
1.54
0.78
1.28
500 - 750 mm
1.16
1.85
0.96
1.54
exc 750 mm
1.23
2.17
1.03
1.82

 

Soffits - On runners and props, on previously erected props etc. 
 

 

Hight of Beam Soffit--->  
 0 - 3.5 m
 
3.5 - 5.0 m
Width
Fix
Strike
Fix
Strike
100 - 200 mm
0.96
1.69
0.91
1.67
200 - 300 mm
1.11
1.92
1.05
1.82
300 - 500 mm
1.27
2.08
1.20
2.00
500 - 750 mm
1.56
2.50
1.49
2.44
exc 750 mm
1.64
2.86
1.39
2.70

 

 

Sides - Strutted from soffit bearers etc.

         

Hight of Beam Soffit--->  
 0 - 3.5 m
 
3.5 - 5.0 m
Depth
Fix
Strike
Fix
Strike
100 - 200 mm
0.78
1.23
0.74
1.18
200 - 300 mm
0.93
1.39
0.88
1.32
300 - 500 mm
1.06
1.54
1.02
1.47
500 - 750 mm
1.47
2.08
1.39
2.00
exc 750 mm
1.54
2.33
1.47
2.33

 

Sides - Using clamps and struts etc. 

Hight of Beam Soffit--->  
 0 - 3.5 m
 
3.5 - 5.0 m
Depth
Fix
Strike
Fix
Strike
100 - 200 mm
0.91
1.47
0.87
1.39
200 - 300 mm
1.09
1.64
1.04
1.56
300 - 500 mm
1.27
1.82
1.20
1.72