Curtain Walling

Curtain Walling rateAssume 30m2 per week for general curtain walling

Started by admin ·
Last updated
Updated
Views
8 views

This page is part of the Rates, Norms & Durations library.

Open the norms tables →

Curtain Walling rate

Assume 30m2 per week for general curtain walling

Task / DescriptionSlow  Ave  Fast   Units
 Vertical Glazed Lights, 6m x 2.5m-  14.5 -   m2/day
 Vertical Glazed Walls, large scale-  70.0 -   m2/day
 Clerestory Frame/Glazing, 3m x 4m-  28.0 -   m2/day
 Oriel Window Frame/Glazing, 4m x 2m-  35.0 -   m2/day
 Glazed Curtain Wall, First Fix-  1.2 -   m2/hr
 Glazed Curtain Wall, Second Fix-  1.1 -   m2/hr
 High Quality Glazed Curtain Walling-  25.0 -   m2/day

2 comments

Oldest first
  1. Richard RJ Tucker ·

    "Assume 30m2 per week for general curtain walling"

     

    Compared to the deatiled rates this comment looks like it should be;

    Assume 30m2 per DAY for general curtain walling

     

    Please confirm

  2. Damien Galllagher ·

    Hi Richard,

    I would agree with you, I think the 30m2 for general curtain walling should be per day.

    Regards,

    Damien