Doors & Window Installation

InstallationFor windows that are not 'built-in' as work proceeds...Install & Fix - By Area = 2.0 m2/hrInstall & Fix - By Girth = 4.0 m/hrMastic Pointing = 6.0 m/hrDoors and Windows

Started by Technical Development ·
Last updated
Updated
Views
8 views

This page is part of the Rates, Norms & Durations library.

Open the norms tables →

Installation

For windows that are not 'built-in' as work proceeds...

  • Install & Fix - By Area = 2.0 m2/hr
  • Install & Fix - By Girth = 4.0 m/hr

Mastic Pointing = 6.0 m/hr

Doors and Windows

Task / DescriptionSlow  Ave  Fast   Units
 Mastic Pointing to Frames-  9.5 -   m/hr
 Fix Metal and Timber Windows After Wall Complete-  2.0 -   m2/hr
 Window Glazing-  1.3 -   m2/hr
 Window Glazing, Single Glazed Units-  2.0 -   m2/hr
 Window Glazing, Double Glazed Units-  1.3 -   m2/hr