Excavate & Reduce Levels

Excavate By Hand Trenches (m3/hr)

Started by admin ·
Last updated
Updated
Views
10 views

This page is part of the Rates, Norms & Durations library.

Open the norms tables →

Excavate By Hand

Trenches (m3/hr)
    

 

Depth in Metres->
Ne 1.5
1.5-3.0
3.0-4.5
 
 
 
 
Sand/Soil lose
0.66
0.45
0.33
Sand/Soil firm
0.57
0.38
0.28
Gravel
0.45
0.31
0.23
Clay/Heavy Soil
0.46
0.31
0.24
Boulder Clay
0.38
0.26
0.19
Pits or Bases Ne 2 m2 (m3/hr)
    
             
Depth in Metres->
Ne 1.5
1.5-3.0
3.0-4.5
Sand/Soil lose
0.5
0.33
 -
Sand/Soil firm
0.43
0.29
  -
Gravel
0.34
0.23
 -
Clay/Heavy Soil
0.35
0.24
 -
Boulder Clay
0.28
0.19
 -
 
    
Hand Transportation of Spoil (m3/hr)
    
      
Wheel
 
0 - 10 m
6.25
10 - 20 m
3.23
20 - 50 m
2.13
    
 
Trim Excavation (m3/hr)
 
            
Ave Thickness
Sand
Gravel
Clay
Boulders
0 - 25 mm
20.00
16.67
20.00
14.29
25 - 50 mm
11.11
 8.33
 9.09
7.69
50 - 75 mm
7.69
 5.88
 6.25
 5.00
75 - 125 mm
 5.56
 4.35
 4.55
 3.70

Reduced Levels (D6 Dozer)

 

Not Ex .25m - 45m3 per hr

Not Ex 1m - 60m3 per hr

Ex 1m - 75m3 per hr