Skip to content
Rates, Norms & Durations

Footing formwork

ActivityTASKSTask - UOMLabor (L) - Carpenter (Mandays)Labor (L) - Helper (Mandays)Material (M)Material (M)Material (M)Footing formworkFooting - Shuttering & Providing SupportSqm0.8 Mandays/10Sqm

Started by admin ·
Last updated
Updated
Views
8 views

This page is part of the Rates, Norms & Durations library.

Open the norms tables →

Activity

TASKS

Task - UOM

Labor (L) - Carpenter (Mandays)

Labor (L) - Helper (Mandays)

Material (M)

Material (M)

Material (M)

Footing formwork

Footing - Shuttering & Providing Support

Sqm

0.8 Mandays/10Sqm

1.5 Mandays/10Sqm

MS Wall Form Panel - 1250 x 500 : 16Nos/10Sqm

Props - 2m to 3m Long : 2 Nos/Rm

Shuttering Oil : 4Ltr/10Sqm

 

Footing - Deshuttering & insitu Stacking

Sqm

0.48 Mandays/10Sqm

0.9 Mandays/10Sqm

   

Comments

No comments yet.

Log in or join to comment