Demolition

Task / DescriptionSlow  Ave  Fast   Units
 Weight, Structural Steel-  2.5 -   Tonnes/m3
 Remove & Cart away, Ceramic Wall Tiles2.0 2.5 3.4  m2/hr
 Remove & Cart away, Wallpaper, 1 layer-  8.7 -   m2/hr
 Remove & Cart away, Wallpaper, 2 layers-  7.1 -   m2/hr
 Remove & Cart away, Wallpaper, 3 layers-  5.7 -   m2/hr
 Remove & Cart away, Lathe and Plaster Ceilings3.2 4.6 5.0  m2/hr
 Remove & Cart away, Plaster to Walls2.1 3.1 5.9  m2/hr
 Remove & Cart away, External Render-  3.9 -   m2/hr
 Remove & Cart away, Floor Screed-  3.2 -   m2/hr
 Remove & Cart away, Concrete Paving-  4.0 -   m2/hr
 Remove & Cart away, Brickwork Walls, 1.0 brick thick-  1.3 -   m2/hr
 Remove & Cart away, Brickwork Walls, 0.5 brick thick-  2.6 -   m2/hr
 Remove & Cart away, Brickwork Walls, Sand/Lime Mortar-  1.8 -   hrs/100
 Remove & Cart away, Fireplace and Hearth-  1.9 -   hrs/no
 Remove & Cart away, Floor Boards-  6.2 -   m2/hr
 Remove & Cart away, Skirting, Architrave, Dado rail etc-  16.5 -   m/hr
 Remove & Cart away, Staircase-  7.3 -   hrs/no
 Remove & Cart away, Windows, 0-1m2-  0.6 -   hrs/no
 Remove & Cart away, Windows 1-2m2-  0.8 -   hrs/no
 Remove & Cart away, Windows 2-3m2-  0.9 -   hrs/no
 Remove & Cart away, Doors-  0.3 -   hrs/on
 Remove & Cart away, Door Frame-  0.1 -   hrs/no
 Remove & Cart away, Floor and Ceiling Joists-  1.1 -   hrs/m
 Remove & Cart away, Wall Plates-  3.9 -   hrs/m
 Remove & Cart away, Iron Bath-  1.4 -   /hrs/no
 Remove & Cart away, Wash Basin/Sink-  0.8 -   /hrs/no
 Remove & Cart away, Pipework including brackets etc-  6.1 -   m/hr