Rates, Norms & Durations
Formwork
In the Open Standard
Started by admin ·
- Last updated
- Updated
- Views
- 8 views
This page is part of the Rates, Norms & Durations library.
Open the norms tables →Formwork
| Task / Description | Slow | Ave | Fast | Units |
| Pilecaps, < 0.7m2 | 0.9 | 1.6 | 2.0 | m2/hr |
| Pilecaps, 0.7-2.5m2 | 1.6 | 2.0 | 2.3 | m2/hr |
| Pilecaps, 2.5-3.0m2 | 2.0 | 2.3 | 2.5 | m2/hr |
| Pilecaps, > 3.0m2 | 2.3 | 2.5 | 3.1 | m2/hr |
| Ground Beams, < 0.7m2 | 1.1 | 1.7 | 1.8 | m2/hr |
| Ground Beams, 0.7-1.5m2 | 1.7 | 1.8 | 2.5 | m2/hr |
| Ground Beams, 1.5-3.0m2 | 1.8 | 2.5 | 2.6 | m2/hr |
| Ground Beams, 3.0-5.0m2 | 2.5 | 2.6 | 3.5 | m2/hr |
| Elevated Plain Slab Soffit | 0.6 | 0.8 | 1.2 | m2/hr |
| Beams, on erected falsework, width 100-200mm | 0.9 | 1.0 | 1.1 | m2/hr |
| Beams, on erected falsework, width 200-300mm | 1.0 | 1.1 | 1.3 | m2/hr |
| Beams, on erected falsework, width 300-500mm | 1.2 | 1.3 | 1.5 | m2/hr |
| Beams, on erected falsework, width 500-750mm | 1.5 | 1.6 | 1.8 | m2/hr |
| Beams, on erected falsework, width over 750mm | 1.4 | 1.5 | 1.7 | m2/hr |
| Walls, Construct Kickers | 5.3 | 7.1 | 10.0 | m2/hr |
| Walls, Fully Framed Formwork/Struts, 1.0-2.0m2 | 0.9 | 1.8 | 1.9 | m2/hr |
| Walls, Fully Framed Formwork/Struts, 2.0-5.0m2 | 1.0 | 2.2 | 2.5 | m2/hr |
| Walls, Fully Framed Formwork/Struts, over 5.0m2 | 1.2 | 2.5 | 2.9 | m2/hr |
| Walls, StoriForm Shutters, 1.0-3.0m2 | 1.0 | 1.4 | 2.0 | m2/hr |
| Walls, StoriForm Shutters, 3.0-5.0m2 | 1.9 | 2.3 | 3.3 | m2/hr |
| Walls, StoriForm Shutters, 5.0-10.0m2 | 2.3 | 2.8 | 3.5 | m2/hr |
| Walls, StoriForm Shutters, 10.0-15.0m2 | 3.2 | 4.5 | 4.0 | m2/hr |
| Walls, StoriForm Shutters, over 15.0m2 | 3.8 | 4.8 | 5.4 | m2/hr |
| Ground Slabs | 1.0 | 1.5 | 1.8 | m2/hr |
| Columns, Construct Kickers, direct to slab | 3.2 | 4.1 | 5.4 | no/hr |
| Columns, Construct Kickers, suspended from soffit slab | 1.2 | 2.8 | 3.2 | no/hr |
| Columns, Square Sides, Timber Clamp/Prop, csa < 0.1m2 | 1.3 | 1.6 | 1.8 | m2/hr |
| Columns, Square Sides, Timber Clamp/Prop, csa 0.1-0.4m2 | 1.8 | 2.1 | 2.4 | m2/hr |
| Columns, Square Sides, Timber Clamp/Prop, csa over 0.4m2 | 2.0 | 2.3 | 2.5 | m2/hr |
| Columns, Square Sides, Steel Forms, 1.5 x 1.5 x 9.0m high | 7.9 | 9.5 | 10.3 | m2/hr |
| Columns, Square Sides, Steel Forms, 2.0 x 2.0 x 9.0m high | 6.9 | 7.5 | 8.3 | m2/hr |
| Columns, Square Sides, Steel Forms, 2.0 x 4.0 x 9.0m high | 8.5 | 10.2 | 12.0 | m2/hr |
| Columns, Round Sides, Sacrificial Plastic Mould, 3.0-4.0m dia | 3.5 | 4.5 | 6.0 | m2/hr |
| Columns, Round Sides, Steel Mould, 3.0-4.0m dia | 5.2 | 6.5 | 7.5 | m2/hr |
| Columns, Sloping Column Heads, extra over rate | - | 2.5 | 3.5 | hrs/no |
| Staircases, Stair Soffit, Sloping | 0.7 | 0.8 | 1.0 | m2/hr |
| Staircases, Stair Soffit, Flat Landing | 0.8 | 0.9 | 1.2 | m2/hr |
| Staircases, Wall Strings | 0.4 | 0.6 | - | m2/hr |
| Staircases, Open Strings | 0.7 | 0.8 | - | m2/hr |
| Staircases, Riser Boards fixed to strings | - | 2.5 | 2.8 | m2/hr |
| Staircases, Risers fixed to Strings | - | 2.3 | 2.6 | m2/hr |
| Waffle Flooring, 2.4m grid | 1.1 | 1.4 | 1.8 | m2/hr |
| Shaft Slip Forming | - | 300.0 | 500.0 | mm/hr |
| Table Form, Aluminum System, 400m2 bays | 2.1 | 3.2 | 3.8 | m2/hr |
| Table Form, H-Frame Steel Falsework, 400m2 bays | 1.9 | 3.0 | 3.5 | m2/hr |
| Tunnel Forms, Wall and Slab poured as one | - | 15.6 | 17.5 | m2/hr |
| Hollorib Decking, lay deck | - | 43.5 | 47.5 | m2/hr |
| Hollorib Decking, shear connecting studs | - | 29.3 | 31.2 | m2/hr |
| Stop Ends, no perforations | 2.8 | 3.5 | 4.2 | m2/hr |
| Stop Ends, minor perforations | 1.2 | 1.5 | 1.9 | m2/hr |
| Stop Ends, dense perforations | 0.9 | 1.1 | 1.4 | m2/hr |
| Box Outs, 0.01-0.05m2 | 7.6 | 8.2 | 9.1 | no/hr |
| Box Outs, over 0.05m2 | 3.1 | 3.9 | 4.5 | no/hr |
| Dummy Frames, under 3.0m2 | 4.5 | 6.2 | 7.1 | no/hr |
| Dummy Frames, over 3.0m2 | 3.1 | 3.7 | 4.5 | no/hr |